Taiwan and India extending PV power project completion dates as COVID-19 impacts

Facebook
Twitter
LinkedIn
Reddit
Email
Taiwan has extended PV power project completion dates on component shortages caused by the coronavirus (COVID-19) outbreak in China, while India is expected to advise policy changes soon. Image: SunEdison

Taiwan has extended PV power project completion dates as a result of component shortages caused by the coronavirus (COVID-19) outbreak in China, while India is expected to advise on policy changes soon. 

Taiwan’s Ministry of Economic Affairs said that PV power plant projects nearing completion in accordance with electricity purchasing rates on relevant projects approved in 2018 and 2019, would be granted a two-month extension, due to component shortages coming from China.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The extensions apply to earlier 2019 projects to June 2020 and later 2019 projects to August 2020.

The Ministry of Economic Affairs stated that it considered the outbreak of COVID-19 an unexpected event, which has had an unpredictable impact on the Taiwanese PV industry.

Chinese PV trade bodies have already requested a similar policy be adopted in China. 

Reports also suggest that India’s Ministry of New and Renewable Energy (MNRE) is expected to announce extensions for completions dates of PV power plants, again due to components coming from China.

Recently, credit agency CRISIL said that around 3GW of PV power plant projects in India were at risk of penalties for missing their respective scheduled commercial operation date (SCOD). India sources over 80% of its solar modules from China, according to CRISIL.

Manish Gupta, Senior Director CRISIL Ratings said, “This puts at risk around 3GW of solar projects auctioned between July and August 2018, which need to meet their SCODs by July 2020. Given that orders for modules are typically placed with a lead time of six months from SCOD, these projects are now in the process of either placing orders or receiving delivery of modules. Hence, any delay at this stage can prove costly.”

Read Next

Premium
November 6, 2026
PV Tech spoke with many industry experts about the midterm election results, covering topics such as permitting, state-level impact and investment appetite.
November 6, 2026
A New South Wales (NSW) parliamentary inquiry has recommended that data centres be legally required to supply their own 100% renewable energy on an hourly basis, a stricter test than the state's current guidelines.
November 5, 2026
IB Solar has signed an MoU with three German companies to develop a 2GW TOPCon solar cell manufacturing line at its facility in India.
November 5, 2026
Essar Renewables has signed a PPA with NHPC Limited for a 300MW firm and dispatchable renewable energy (FDRE) project in Andhra Pradesh.
November 5, 2026
EDP Renewables North America has begun work on its 250MW Cypress Knee Solar project in Arkansas, which will eventually supply power to tech giant Meta.
November 5, 2026
Tristan Erion-Lorico and Song Hao of Kiwa PVEL examine the negative consequences of overreliance on module nameplate power ratings for PV project economics.

Upcoming Events

Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
February 2, 2027
London, UK
Solar Media Events
April 20, 2027
Istanbul, Türkiye