Solar beats natural gas in landmark US judicial ruling

Facebook
Twitter
LinkedIn
Reddit
Email

An administrative judge in the US state of Minnesota has ruled solar generation to be a better investment than natural gas for electric and natural gas utility, Xcel Energy.

The judgment is the first time in the US that unsubsidised solar energy has been officially ruled to be a better deal for ratepayers than natural gas in a competitive bidding process.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The competitive bidding of utility-scale generation projects was ordered by Minnesota’s Public Utilities Commission to choose the most cost-effective projects to help Xcel reach what the commission said was an additional 150MW of new capacity needed by 2017.

Administrate judge Eric Lipman compared five energy resources to determine the most cost-efficient generation to meet forecast energy shortfalls. A 100MW PV project by Minnesota-based utility-scale wind and solar developer, Geronimo Energy, was chosen over the others.

Geronimo proposed to build 20 solar parks, across 17 counties in Minnesota – some as big as 70 acres and costing an estimated US$250 million. Named the ‘Aurora Solar Project’, Geronimo’s solar project would receive no state or utility subsidies, but would qualify for a federal investment tax credit. The Aurora project is approved, with completion expected by 2016.

In his ruling Lipman said the project was the best way for Xcel to meet its near-term needs.

Judge Lipman ruled if solar is not sufficient to meet Xcel’s surplus energy demand, the utility should consider purchasing power from one of its competitors.

Solar was considered in comparison to a gas turbine at an existing plant in Mankato, proposed by Calpine, and two turbines at Cannon Falls and Hampton, proposed by Invenergy, as well as Xcel’s own proposal for a gas plant.

Lipman’s ruling still needs to be upheld by the Public Utilities Commission.

The commission has a six to eight-month window to review and process Excel’s energy resource plans.

In evidence given to the hearing in November, Excel disputed the commission’s estimates of its required new capacity, suggesting this week’s ruling may be challenged.

But Geronimo’s vice president of development, Elizabeth Engelking noted at the evidentiary hearing that “while Xcel’s overall need in megawatts may be uncertain, there is no uncertainty regarding Xcel’s need to add solar resources.”

Read Next

November 12, 2026
Terra-Gen completes PV park in California, Duke Energy Florida plans four new solar arrays, and Altus Power acquires another 92 projects.
November 12, 2026
Investing in a portfolio that includes solar PV projects and BESS is a key tool to reduce exposure to price risk, according to Pexapark.
November 12, 2026
SMA Solar has narrowed its full-year guidance for 2026 towards the upper half of its previously raised range after reporting improved financial results for the first nine months of 2026.
Premium
November 12, 2026
Module testing challenges, the role of BESS and the procurement landscape were key topics of conversation at PV ModuleTech Europe 2026.
Sponsored
November 12, 2026
If two modules carry a Class A designation, how much can we actually conclude about their fire performance?
November 12, 2026
Almost 2GW of PV capacity is to be put out to tender in the latest phase of Saudi Arabia’s renewable energy procurement programme.

Upcoming Events

Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
February 2, 2027
London, UK
Solar Media Events
April 20, 2027
Istanbul, Türkiye