UK grid connection reform to unlock 65GW of utility-scale solar

By Molly Green and George Heynes
Facebook
Twitter
LinkedIn
Reddit
Email
A NextEnergy Capital project in the UK.
The grid connection reform could also unlock 7.6GW of battery energy storage system (BESS) capacity by 2030. Image: NextEnergy Capital.

UK energy regulator Ofgem has approved plans to remove so-called ‘zombie projects’ from the country’s grid connection queue, and streamline the connection process for renewable power projects that are most needed, which could trigger an increase in proposals for new PV projects in the UK.

The long-anticipated grid connection reforms were first put forward by the National Energy System Operator (NESO) with the aim of reducing the number of projects awaiting connection to the UK electricity grid.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

According to the Department for Energy Security and Net Zero (DESNZ), companies are currently waiting up to 15 years to be connected, with the length of the queue growing tenfold in the last five years.

Ofgem said that as of February 2025, 756GW worth of projects were in the queue, with 587GW at transmission and 178GW on the distribution network. These figures far exceed what is needed for either Clean Power 2030 (CP30) or net zero by 2050.

As such, the regulator has made good on its minded-to decision to approve the reforms. The details of how the new process will work are mostly unchanged from earlier this year.

The move is anticipated to be a major boon to the UK’s solar PV sector. According to a spokesperson from the energy regulator, Ofgem expects a sizeable increase in Gate 2 offers, from 39GW to 65GW. Trade association Solar Energy UK also believes the reformation of the grid connection queue is likely to spearhead utility-scale solar PV developments.

“Reforming the connections queue is critical to reaching Clean Power by 2030 and paving the way for the 60GW industry to deliver. While we welcome Ofgem’s announcement in principle, the government must ensure network operators do not impose arbitrary caps that disadvantage solar and battery storage,” Chris Hewitt, CEO of Solar Energy UK, said.

“Restricting viable projects would undermine the pipeline needed to achieve the government’s energy mission and contradicts its call to ‘choose Britain’ for investment.”

Read the full version of this story on our sister site, Solar Power Portal.

Read Next

July 17, 2026
Renewable energy generation is now accelerating faster than energy systems can absorb it, according to Schneider Electric's Frédéric Godemel.
Premium
July 17, 2026
PV Talk: Solclaris' Joe Miletic discusses the 'ready-to-repower' stage of PV project O&M and how it differs from the 'ready-to-build' stage.
July 17, 2026
German solar inverter producer SMA Solar has raised its full-year 2026 financial guidance following its preliminary Q2 financial results.
July 16, 2026
German solar energy research institute ISC Konstanz has appointed Dr Gerhard Mathiak as its head of its module department.
July 15, 2026
Solar power saved the European Union €20 billion (US$22 billion) in gas imports between 1 March and 15 July, according to SolarPower Europe.
July 15, 2026
Qualitas Energy has secured a €53 million (US$63 million) non-recourse financing package for a 117MWp greenfield solar PV portfolio in Poland.

Upcoming Events

Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
April 20, 2027
Istanbul, Türkiye