US solar facing fresh shipment delays as UFLPA enforcement raises quartzite queries

Facebook
Twitter
LinkedIn
Reddit
Email
The UFLPA came into force on 21 June. Image: Port Houston.

The US solar industry is facing fresh module shipment delays after new import documentation was demanded by Customs and Border Protection (CBP).

As part of the country’s new Uyghur Forced Labor Prevention Act (UFLPA) enforcement process, CBP is now requesting documentation showing the source of quartzite used in the polysilicon manufacturing process.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

A research note issued by Philip Shen of investment bank ROTH Capital Partners has suggested that shipments to the US from Southeast Asia could be delayed by up to 12 months as a result, with module manufacturers said to be lacking documentation of that kind.

Shen, who also noted that shipments of one leading module manufacturer have already been seized, said the enforcement “could be a major headwind near-term”.

The development follows the UFLPA coming into force on 21 June. Among the act’s key provisions is a requirement that CBP apply a “rebuttable presumption” that all goods produced or manufactured wholly or in part in China’s Xinjiang region are presumed to be made with forced labour and are prohibited from entry into the US.

Xinjiang produces about half of the world’s polysilicon, which is among the high-priority sectors for UFLPA enforcement.

CBP has previously asked about the source of quartz supply under the Hoshine withhold release order (WRO), according to Christian Roselund, a senior policy analyst at supply chain traceability firm Clean Energy Associates (CEA), who said it is unclear at this point if Customs is asking for a higher standard of documentation for quartz supply than it did in the past.

“There appear to be different levels of preparedness at different suppliers regarding documentation of quartz supply,” Roselund said. “And while detentions create uncertainty in the market, some of the largest suppliers are still shipping to the United States.”

In guidance published earlier this month, CBP said importers may consider submitting a flow chart mapping each step in the procurement and production of all materials and identify the region where each material in the production originated, such as the location of the quartzite used to make polysilicon.

The guidance said importers should be aware that imports of goods from factories that source polysilicon both from within Xinjiang and outside of Xinjiang risk being subject to detention, as it may be harder to verify that the supply chain is using only non-Xinjiang polysilicon and that the materials have not been replaced by or co-mingled with Xinjiang polysilicon at any point in the manufacturing process.

The Department of Homeland Security earlier this month published a list of entities whose products are alleged to be made with forced labour and are banned from entering the US. Among the companies that appear on the list are Hoshine Silicon and subsidiaries of polysilicon producers Daqo, East Hope and GCL.

A report published in February by the US Department of Energy said the impact of UFLPA on the solar supply chain “could be profound” over the years the act is in effect (2022 – 2029) if the Chinese government prevents solar companies from providing the documentation required by the Forced Labor Enforcement Task Force to prove their goods are compliant.

Wacker, which supplies solar-grade polysilicon from its plants in Germany and the US, “successfully supported its polysilicon customers under the previous WRO ruling and will continue to do so under the new UFLPA requirements”, said Christian Westermeier, vice president of sales, marketing and application technology at Wacker Polysilicon.

Westermeier added: “Across the globe, Wacker is upholding human rights and expects the same of partners and suppliers.”

Read Next

Premium
August 21, 2026
PV Tech Premium speaks with United Solar about the challenges of building polysilicon capacity outside of China and catering to the US and Indian markets.
August 21, 2026
Daqo New Energy reduced its losses in Q2 2026 and increased its revenues, largely by resuming polysilicon sales below the cost of production.
August 21, 2026
Australia has extended a CGT concession for foreign investors in wind, solar and BESS by a further decade, pushing the deadline to June 2040.
August 19, 2026
A patent infringement lawsuit filed by Maxeon against Canadian Solar has been dismissed with prejudice in the US Federal District Court.
August 18, 2026
Risen Energy has signed an MoU with Ascania Energy to deploy 100MW of solar PV capacity and 200MWh of utility-scale batteries in Ukraine.
August 18, 2026
Tax credit transfer value in the US rose between the second half of 2025 and the first half of 2026, according to Crux.

Upcoming Events

Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
February 2, 2027
London, UK
Solar Media Events
April 20, 2027
Istanbul, Türkiye