Vena Energy adds batteries to 87MW PV plant in South Australia

Facebook
Twitter
LinkedIn
Reddit
Email
A Vena Energy project.
ZEN Energy will purchase renewable energy from the Tailem Bend 2 solar-plus-storage project. Image: Vena Energy.

Singaporean independent power producer (IPP) Vena Energy has added a 41.5MW battery energy storage system (BESS) to a 87MW solar PV power plant in South Australia.

The addition of the BESS marks the successful commissioning of the Tailem Bend 2 Hybrid Project. The solar-plus-storage site is situated across 207 hectares in Tailen Bend, around 90km southeast of the state capital, Adelaide.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Adelaide-headquartered renewable energy developer ZEN Energy will purchase renewable energy from the Tailem Bend 2 solar-plus-storage project, underpinned through a long-term commitment from the South Australian Chamber of Mines and Energy (SACOME) Joint Electricity Purchasing Group.

This agreement will support customers, including the majority of local Foodland and IGA supermarkets, Viterra, Central Irrigation Trust, Adchem, and Hillgrove Resources.

Vena confirmed that the project will connect to the National Electricity Market (NEM) via ElectraNet’s Tailem Bend Substation from the Coorong 2 Substation. The BESS will serve as a load and generator for the network by capturing low-cost renewable energy to be discharged at peak demand.

“Our system enables simultaneous export of solar power to the grid and independent operation of the battery for energy export or storage,” said Owen Sela, head of Australia for Vena Energy. “By optimising existing grid infrastructure, we are enabling renewable energy to be dispatched when needed, delivering cost-effective power to South Australia.”

“This ability to store surplus energy and meet high-demand periods advances our mission to accelerate the energy transition while ensuring communities benefit from a smarter, more resilient energy system that supports the state’s 2030 emissions targets and Australia’s net zero future.”

Read the full version of this story on our sister site, Energy-Storage.news.

Read Next

July 31, 2026
The Colombian Ministry of Mines and Energy has awarded 995MW of solar PV and nearly 100MW of battery energy storage system (BESS) in a clean energy procurement auction.
July 31, 2026
Australia's installed cost of utility-scale solar has not fallen at the pace required to reach the country's “ultra-low-cost solar” (UCLS) ambitions, despite continued progress in cell and module efficiency.
July 31, 2026
Queensland and Northern Territory have refused to back a national framework requiring large data centres to underwrite new renewable energy.
July 30, 2026
EDPR has agreed to sell an 80% equity stake in a 384MW solar-plus-storage portfolio in the US to a Private equity firm Ares Infrastructure.
July 30, 2026
Walden has secured US$250 million from Crayhill Capital Management to support its 5GW US utility-scale solar PV and BESS pipeline.
July 30, 2026
Array has launched a suite of foundation-to-tracker solutions to improve the connections between Array trackers and foundations.

Upcoming Events

Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
April 20, 2027
Istanbul, Türkiye