BSW-Solar calls for simplified grid access for German solar and storage projects

September 12, 2025
Facebook
Twitter
LinkedIn
Reddit
Email
Front view of the Bundestag, Germany's Federal Parliament.
A survey from BSW-Solar found that grid access in Germany needs to be simplified, standardised and more digitalised. Image: Alana Harris via Unsplash.

German trade association BSW-Solar has called the German government for a simplified, standardised and more digitalised grid access for solar PV and energy storage operators.

These were the main findings of a survey conducted by BSW-Solar among project developers in Germany.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Solar companies that replied to the survey criticised the poor communication with many of the more than 800 grid operators in Germany, as well as the slow process with grid connection requests.

Respondents of the survey also criticised the slow process for large-scale battery energy storage systems (BESS). A majority of the respondents (63%) said that requests for co-locating solar with storage ended up with either no response for the grid connection request, a rejection or a notification that grid connection will not be possible until the end of 2028.

Carsten Körnig, managing director at BSW-Solar, commented: “The often poor communication of grid operators is increasingly hindering the energy transition. In the future, politicians must hold them more accountable for standardising and digitising their processes and adhering to binding deadlines.”

Moreover, survey respondents identified the lack of transparency regarding grid capacities as the biggest obstacle for the construction of ground-mounted solar PV systems. This was followed by a failure to comply with deadlines to provide information and a lack of personnel resources from grid operators.

According to the trade association, the average time to receive a successful grid connection can be less than four months, with the more extreme cases reaching years.

Amidst the survey results, the German trade association called on the government to amend the Energy Industry Act through five key points.

These are to increase grid transparency by introducing non-binding grid connection information, enabling project developers to obtain information before submitting a grid connection request; creating binding reservation options for network capacities that take appropriate account of project progress in order to improve planning and investment security for project developers and to avoid blockages caused by unused commitments; digitalisation of grid connection requests; universalise the deadlines in the grid connection process and sanction non-compliance; and introducing a right to “overbuild” grid connection points in regards to the grid operator, in order to more efficiently use the limited grid capacity with the co-location of energy storage.

The last point is due to 90% of the companies surveyed stating that they plan to submit applications for co-located ground-mounted solar PV with BESS in the future, where the installed generation capacity exceeds the agreed feed-in capacity.

Read Next

February 24, 2026
Increased renewable energy penetration in Europe's leading clean energy markets will lead to more fluctuations in power prices.
February 23, 2026
Developer FRV is to hybridise a swathe of its Spanish PV fleet with batteries as part of a wider storage push in the country.
February 19, 2026
German solar wafer manufacturer NexWafe and US-based cell producer Talon PV have signed a wafer supply agreement in the US.
February 18, 2026
Meralco PowerGen Corporation has completed initial grid synchronisation and energisation of the 3.5GW MTerra solar project, which includes a 4.5GWh battery energy storage system (BESS). 
February 16, 2026
A 77.5MW PV plant in Estonia is to be coupled with a 55MW/250MWh battery energy storage system to create what is claimed will be the country’s largest hybrid project.
February 16, 2026
Enfinity has expanded a bond facility with the Eiffel Investment Group to US$183 million, to further its work in US solar and BESS.

Upcoming Events

Solar Media Events
March 24, 2026
Dallas, Texas
Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA
Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain