Frontier Energy signs AU$280 million debt facility for Waroona solar-plus-storage project in Western Australia

Facebook
Twitter
LinkedIn
Reddit
Email
Frontier Energy’s Waroona Renewable Energy Project (pictured) will include a 132MW solar PV power plant. Image: Frontier Energy.

ASX-listed Frontier Energy has executed an AU$280 million (US$196 million) syndicated debt facility for Stage One of its 132MW Waroona solar-plus-storage project in Western Australia.

The senior secured, non-recourse debt will fund construction and operation of the first stage, which pairs a 132MW solar PV plant with an 81.5MW/562MWh battery storage system about 120km south of Perth.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Frontier informed the exchange on 2 November that the agreement was signed through its wholly owned subsidiary WRP Finance. It follows the credit-approved underwriting letter and term sheet the company announced on 17 July, shortly before it appointed Monford Group as engineering, procurement and construction (EPC) contractor.

The lending syndicate is led by Natixis Corporate & Investment Banking (Natixis CIB) and Sumitomo Mitsui Banking Corporation (SMBC). Natixis CIB is the investment banking arm of France’s Groupe BPCE, while SMBC is the main banking business of Japan’s Sumitomo Mitsui Financial Group. Frontier has not named the other members of the syndicate.

The facility is split into three parts: a construction and term facility of up to around AU$250 million, a bank guarantee facility of up to AU$13 million and a debt service reserve facility of up to AU$17 million. Frontier said in July that all three qualify under the Green Loan Principles.

Legal maturity is three years from financial close, with a one-year extension available at each lender’s discretion. Repayments are sculpted over a notional 18-year period.

Frontier said the debt, together with the AU$110 million equity placement completed in July, is expected to fully fund Stage One through to first generation in 2028. At the time of the equity raise, the company said it was seeking senior debt to cover up to 70% of Stage One funding.

Financial close is expected in November, subject to conditions precedent. These include signing a Capacity Investment Scheme (CIS) agreement with the federal government and entering interest rate hedging to fix the rate over the term of the construction facility.

Frontier said both conditions will be satisfied “in the coming weeks”, with first drawdown forecast for the first quarter of 2027.

Jamie Cullen, executive chair of Frontier, said execution of the facility “comes as site works at Stage One are ramping up”. He thanked Azure Capital, which acted as the company’s debt finance advisor.

Revenue support, EPC and battery storage contracts in place

The CIS is a federal revenue-underwriting scheme under which the government makes top-up payments if a project’s revenue falls below an agreed-upon floor.

In May, Waroona Stage One was one of three battery storage projects selected under Tender 6, as Western Australia awarded 1.9GW of renewables and 3.7GWh of battery storage under CIS Tenders 5 and 6. Frontier said the award gives the project downside revenue protection until 2042. The floor price has not been disclosed.

The project has changed shape since Frontier acquired the original developer, Waroona Energy, in late 2023. In 2024, the company lined up AU$215 million of debt from Infradebt for a 120MW first stage, but the project was paused that October after it missed out on Reserve Capacity Credits from the Australian Energy Market Operator (AEMO).

Solar capacity has since risen to 132MW through a switch to 660W modules, and storage duration was extended to 6.9 hours to meet a 6-hour minimum under the state’s reserve capacity rules.

Monford, a Western Australian contractor that previously built the 128MWdc Cunderdin solar-plus-storage plant, holds a fixed-price EPC contract and will take AU$5 million of its contract value in Frontier shares. In September, Frontier contracted Trina Storage to supply the 562MWh battery storage system, with a 20-year warranty and a long-term services agreement.

Frontier buys the main equipment under fixed-price contracts and passes it to Monford, which takes delivery at Fremantle Port.

The company said the first trackers are due in November 2026 and the first solar modules in January 2027. Its connection agreements with Western Power allow exports of up to 99MW and imports of up to 95MW to charge the battery storage system.

Frontier plans a staged build-out to around 1GW of solar and 660MW of battery storage by 2031. Stage Two, of about 120MW of solar and 80MW of storage, already has development approval.

The pipeline sits alongside the state government’s target of 75% renewable energy on the South West Interconnected System (SWIS) by 2030-31, with the state’s coal-fired generation scheduled to retire by 2030. Cullen said Frontier will “continue to work through future expansion opportunities”.

Read Next

November 23, 2026
US solar firm SunPower reported Q3 2026 revenue of US$65.1 million, up US$10.2 million from the previous quarter.
November 23, 2026
As rooftop solar in India surges, the country's energy ministry is offering grants of up to INR300 million to 15 discoms to deploy distributed energy management systems.
November 23, 2026
Chinese home-appliance giant Skyworth Group is aiming to initiate the spin-off and listing of its subsidiary, the leading residential solar firm Skyworth PV, by the end of this month.
November 23, 2026
The CEO of US thin-film PV manufacturer First Solar has called for bipartisan policy support for US tariff programmes and praised the measures introduced by the Trump administration to limit non-US solar companies’ access to the US market.
Premium
November 23, 2026
IEEFA says India could unlock INR680 billion in renewable investment through life insurers, addressing domestic funding constraints.
November 23, 2026
JK Cement will acquire a 27.03% stake in Hero Future Energies-backed SPV to secure solar power for its Karnataka plant.

Upcoming Events

Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events, Upcoming Webinars
December 9, 2026
9am GMT / 10am CET
Solar Media Events, Upcoming Webinars
December 16, 2026
9am PST
Solar Media Events
February 2, 2027
London, UK
Solar Media Events
April 18, 2028
Istanbul, Türkiye