India adds 11GW solar PV in Q3 2025 – IEEFA

November 26, 2025
Facebook
Twitter
LinkedIn
Reddit
Email
Sunsure Energy's Jhansi solar project in India.
Between January and September 2025, India saw 29.5GW of solar PV additions. Image: Sunsure Energy.

India has added 11GW of solar PV capacity during the third quarter of 2025, according to a report from the Institute for Energy Economics and Financial Analysis (IEEFA).

This is the second quarter in a row where India saw more than 10GW of new solar PV added, trebling the average quarterly numbers from 2022 that were about 3.5GW.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Solar PV accounted for 69% of the 16GW of new power generation capacity added in India during Q3 2025, bringing solar’s total installed capacity in the first nine months of 2025 to 29.5 GW. This represents a 68.9% increase from the same period a year ago, when India registered 17.4GW of solar PV additions. As of the end of September 2025, India had over 127GW of installed solar PV capacity, the most of any renewable energy resource, and only behind coal power, with 224GW.

Rooftop solar has also witnessed renewed interest in 2025, according to IEEFA, with 5.8GW of capacity additions between January and September 2025. This represents an 81% increase from the same period last year. IEEFA numbers are slightly higher than those from market research firm Mercom India, which estimates that 4.9GW of rooftop solar capacity was added in the first nine months of 2025. Nearly half of this year’s rooftop PV additions came from Q3 2025 with 2.1GW added in the quarter, according to Mercom India.

Moreover, the removal of the 100% waiver of inter-state transmission system (ISTS) charges from 1 July 2025 for standalone solar PV and wind projects has accelerated the commissioning of renewable energy projects, according to IEEFA. The charges are set to be reintroduced by July 2028. On top of this, the favourable economics of renewable energy plants, with or without co-located storage, and a positive policy scenario have driven the growth of renewables in India, added IEEFA.

With three more months to go before final numbers for PV additions in 2025 are available, India has already surpassed the totals from all of 2024.

Indeed, India added more than 24.5GW of solar capacity in 2024, according to data from energy consultancy JMK Research. Last year was already a record year for the country, which saw continued growth in PV installations, matched at the upstream level by more than 100GW of domestic annual nameplate capacity for modules.

Furthermore, investments in the renewable energy industry continue to increase in India. During Q3 2025, US$5.2 billion was invested in renewable energy, a 112.6% year-on-year increase. This brings the total investments until the end of September to US$18 billion, numbers that are far above the totals registered in 2022 (US$US$15.2 billion), 2023 (US$13.2 billion) and 2024 (US$10 billion).

“Global private equity and sovereign funds are showing heightened interest in India’s renewable energy sector, spurred by supportive energy transition policies and sustained economic growth. While solar power remains the primary driver of India’s energy transition, emerging hybrid applications and the integration of energy storage to deliver firm power are further accelerating investment momentum,” said IEEFA.

However, the accelerated growth of solar PV additions in India has also been met with an increase in solar curtailment, said IEEFA. Reports from the Grid Controller of India showed that curtailments of solar PV rose by 12% between May 2025 and October 2025.

Due to the accelerated growth of solar PV and wind installations, the grid has struggled to keep pace. The grid challenge, along with recent tender issues, was one of the main focus points of a recent PV Talk (subscription required) with Abhinav Jindal, deputy general manager at Power Management Institute (PMI).

Read Next

Premium
March 5, 2026
Analysis: Just as the energy crisis following Russia’s invasion of Ukraine led to a European pivot on clean energy, the US-Israel war on Iran presents another potential turning point, this time with a wider global reach.
March 4, 2026
ISC Konstanz has partnered with Celloraa Energy to develop a 1.2GW TOPCon cell production facility in Gujarat, India.
March 4, 2026
Group Surya has commissioned a G12R module manufacturing facility in Odisha, the first such manufacturing facility in the Indian state.
March 4, 2026
Australia's utility-scale solar PV and wind assets delivered a combined 5TWh of generation in February 2026.
March 3, 2026
Average PV equipment costs for large-scale solar projects in India showed mixed trends in Q4 2025, said Mercom.
March 2, 2026
India is expected to add 42.5GW of new solar capacity in 2026, according to research analyst JMK Research’s Q4 2025 (Oct-Dec) India RE Update report. 

Upcoming Events

Solar Media Events
March 24, 2026
Dallas, Texas
Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA
Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain