New guidelines for Indian solar power procurement to bring confidence to the sector

By Bridge to India, a leading consultancy in India's renewables market
Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn
Share on reddit
Reddit
Share on email
Email
The Bridge to India team Credit: SunEdison

The Ministry of Power has issued new “Guidelines for tariff-based competitive bidding process” for solar power plants. The guidelines shall be applicable to all projects equal to or greater than 5MW for supplying power directly/indirectly to distribution comapnies (Discoms) subject to approval from the respective central or state regulator. For the first time in the sector, the government also proposes to issue standard bid documents including request for selection, PPA and other ancillary documents.

The proposed changes, while still not going far enough, are a major improvement on the current framework. Introduction of standard documentation, in particular, will be of major help to developers and investors. Significant changes are discussed below:

Readiness of project site:

The guidelines specify strict timelines for completion of land acquisition, transmission connectivity and other approvals in a timebound manner to avoid project delays. If the power purchaser retains responsibility for these in the form of a solar park, then it must ensure that: i) at the time of bidding, 100% of land is identified and proof of in-principle availability of 25% of land is in place; and ii) within one month of PPA signing, 90% of land is acquired and balance 10% is acquired in the next two months. All statutory clearances and transmission connectivity feasibility should be available prior to PPA signing.

If there is no solar park available, the developer must: i) have identified 100% of land requirement at the time of bid submission and complete full land acquisition within 7 months from the date of PPA signing. It must also ensure that environment/forest clearances, approval for water and transmission technical feasibility are available.

Payment security mechanism:

In addition to a letter of credit for one-month billing, the power purchaser (Discom or an intermediary buyer such as NTPC/SECI) needs to establish a payment security fund equivalent to three-month billing amount. This is a major improvement over current practice and will help in reducing Discom payment risk perception.

Where Discoms are buying power through an intermediary entity such as NTPC/SECI, they are required to procure a state government guarantee in favour of NTPC/SECI if a tripartite agreement between the respective state government, Reserve Bank of India and the central government is not in place.

Compensation for offtake constraints:

The guidelines recognise that grid backdowns/curtailment are becoming a bigger problem for the sector and seek to provide compensation to developers for the same. In the event of generation loss due to evacuation infrastructure not being ready or being unavailable for more than 50 hours in a year, the developers are allowed to sell equivalent amount of extra power over subsequent three years. In the event of back-down requests from Discoms, 50% of revenue shortfall will be met by the Discom. However, there is no compensation for any backdowns due to grid instability or safety reasons.

These clauses are a positive step but they still do not provide sufficient protection to the developers from curtailment or back-down risks.

Termination compensation:

It is unbelievable that most solar PPAs in India today do not have any provision for termination compensation for a power purchase default. The new guidelines specify that the developer can terminate the PPA in case of a power purchaser default and seek compensation equivalent to total debt outstanding plus 150% of adjusted equity, or six months billing amount, whichever is lesser. The introduction of this clause will serve as a major deterrent against default and protect the developers from Discoms seeking to unilaterally cancel or re-negotiate PPAs.

Lender substitution rights:

The new standard PPA will allow substitution if the developer defaults on payments to its lender(s). Previously, substitution was permissible only if the developer had defaulted on its PPA obligations.

These changes have come after extensive consultations and aim to protect developer and investor-lender interests. As we saw with the recent Rewa tender, improved contractual documentation and risk allocation can provide more confidence to the sector and lead to a win-win arrangement for all parties.

Read Next

January 14, 2022
The US Department of Energy (DOE) has launched a “Building a Better Grid” initiative to catalyse the development of “new and upgraded high-capacity electric transmission lines” across the US under President Joe Biden’s US$1 trillion Bipartisan Infrastructure Law.
PV Tech Premium
January 14, 2022
Raising more than US$1 billion in equity capital in the past year, US independent power producer (IPP) Silicon Ranch is looking to expand its model of developing, owning and operating large-scale PV plants while maintaining a strategy of co-locating projects with regenerative agriculture.
January 13, 2022
Reliance Industries has signed a Memorandum of Understanding (MoU) with the government of Gujarat for a total investment of INR5.955 lakh crore (US$80 billion) over 10-15 years to establish 100GW of renewables and set up green technology manufacturing facilities in the state.
January 11, 2022
Solar PV power generation in Vietnam could about to be maximised through the integration of battery energy storage systems (BESS), with consultancy AqualisBraemar LOC Group (ABL Group) hired to conduct feasibility studies across multiple PV plants following curtailment issues in the country.
January 10, 2022
Indian renewables company ReNew Energy Global Plc’s wholly owned subsidiary India Clean Energy Holdings has raised US$400 million through a green bond sale that will be used to support the company’s growth strategy and “refinance existing high-cost debt”.
January 10, 2022
Indian conglomerate Adani Group has set up a new subsidiary focused on areas including manufacturing solar equipment and producing green hydrogen.

Subscribe to Newsletter

Upcoming Events

Upcoming Webinars
January 26, 2022
Free Webinar
Solar Media Events
February 23, 2022
London, UK
Solar Media Events
March 8, 2022
London, UK
Solar Media Events
March 23, 2022
Austin, Texas, USA
Solar Media Events
March 29, 2022
Lisbon, Portugal