New US solar permitting challenges can be overcome

By Allison Chapin & Michael Downs
January 22, 2026
Facebook
Twitter
LinkedIn
Reddit
Email
Newly tightened federal permitting rules for solar and wind projects in the US create fresh hurdles for developers. Image: Burns & McDonnell.

Utility-scale solar developers face a number of complex challenges. Permitting a solar project may seem like a daunting task, but the process can be overcome with a strategic approach and smart scheduling.

Due to recent federal policy directives in the US, electric generation projects that prioritise maximum energy density per acre now enjoy favoured status. Implemented following an executive order issued by the current administration in early 2025 that declared a national energy emergency, new solar generation projects that require federal review now face permitting hurdles that could jeopardise the schedule, reduce generation capacity or even cause project cancellations — that is, without appropriate planning.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Following Executive Order (EO) 14315, “Ending Market Distorting Subsidies for Unreliable, Foreign-Controlled Energy Sources”, the Department of the Interior (DOI) issued a memorandum on 15 July 2025, “Departmental Review Procedures for Decisions, Actions, Consultations, and Other Undertakings Related to Wind and Solar Energy Facilities.” This clarifying guidance now requires wind and solar-related matters within DOI’s purview to be routed through three levels of departmental review. These include:

  • Submission to the Office of the Executive Secretariat and Regulatory Affairs
  • Subsequent review by the Office of the Deputy Secretary
  • Final review by the Office of the Secretary

Among the memo’s covered items:

  • Section 106 compliance and other cultural resource consultations
  • Consultation and permits under the Endangered Species Act, Migratory Bird Treaty Act, Bald and Golden Eagle Protection Act
  • Biological assessments and biological opinions

Because the memo adds high-level review steps without a defined decision timeline, it may increase schedule uncertainty for wind and solar projects requiring DOI actions or consultations. These consultations have traditionally been performed from local field offices.

What it all means

If your project has a federal nexus, it may trigger federal environmental review and interagency consultation. These triggers may include:

  • Development on or crossing federal land (e.g., Bureau of Land Management-managed land)
  • Federal authorisation/right-of-way
  • Federal funding
  • Clean Water Act Section 404 permit from the U.S. Army Corps of Engineers for impacts to jurisdictional waters and wetlands
  • The potential for take or impacts to federally listed species

Depending on the project’s impacts, this can include consultation with the DOI, most commonly through the U.S. Fish & Wildlife Service for Endangered Species Act compliance, and through DOI land-management bureaus when DOI is the authorising land manager. Section 106 review for historic and cultural resources is led by the applicable federal action agency in consultation with SHPO/THPO, tribes and other parties. DOI is typically involved only when it is the action agency or if it is managing the affected lands/resources.

The best approach is to avoid and minimise impacts to jurisdictional waters/wetlands, listed species, critical habitat and cultural resources. Reducing permitting and consultation scope is expected to lower the likelihood of additional federal review layers.

If impacts to sensitive resources are unavoidable and permitting/consultation is required, schedule uncertainty can increase due to agency coordination, information needs and consultation timelines. For projects requiring DOI authorisations or DOI-led review, additional departmental review steps may further affect timing.

This directive creates the high likelihood that projects that formerly required only routine federal reviews from the local office now face long delays in getting on calendars for reviews by highly placed agency officials.

Though the policy changes don’t completely forestall the possibility that projects could advance, there is still a higher risk that projects could have schedule delays or be cancelled altogether if developers do not minimise impacts and schedule consultation reviews appropriately.

Strategic risk opportunity and mitigation

With the policy now in place, teams should implement creative strategies to avoid triggering consultations and additional federal review wherever possible.

“Smart scheduling” is one such strategy. It starts with incorporating seasonal restrictions on tree clearing, vegetation removal and other activities within or adjacent to sensitive resources into the overall project schedule. Smart scheduling also starts with desktop screening to identify potential sensitive resources and to plan targeted field surveys to confirm which species are present and which vegetation communities may serve as habitat.

For example, if tree clearing is required, it should first be minimised and then reviewed to confirm it will not occur in known critical habitat or near a hibernacula or maternity roost. If that is the case, tree clearing should be scheduled during winter hibernation months to reduce or eliminate impacts on listed bat species.

Beyond vegetation clearing considerations, sites should be evaluated early to avoid or minimise impacts to streams and wetlands, cultural or historic resources, and threatened and endangered species. For instance, stream and wetland impacts can sometimes be limited to temporary impacts that avoid triggering additional federal review, or kept below the pre-construction notification thresholds for a Nationwide Permit. If the project can comply with Nationwide Permit conditions and remain below applicable thresholds, additional reviews may be avoided.

The impact of these regulatory hurdles can also be softened by working with engineering-procurement and construction (EPC) teams. This project delivery model emphasises close integration with environmental professionals to collaboratively design projects that are constructable while keeping impacts to sensitive resources within permissible limits.

Solar finds a way

Though solar energy projects are being slowed due to recent federal actions, the pathways for permitting success still are available. It just takes careful planning, strong collaboration and smart scheduling.

Alisson Chapin is department manager, environmental services, at Burns & McDonnell. Michael Downs is a staff environmental scientist at Burns & McDonnell.

Read Next

March 3, 2026
Singapore has raised its solar PV deployment target to 3GW by 2030 after reaching its previous 2GW target in 2025.
March 3, 2026
A consortium of companies led by Global Infrastructure Partners (GIP), a subsidiary of global asset owning giant BlackRock, is set to acquire US utility AES Corporation in a US$10.7 billion deal. 
March 3, 2026
Average PV equipment costs for large-scale solar projects in India showed mixed trends in Q4 2025, said Mercom.
March 3, 2026
Solar racking producer Schletter Group has completed construction on a 96MWp solar PV project in northern Italy.
March 2, 2026
Virya Energy has secured US$99 million (€85 million) in equity from EBRD to acquire and scale a portfolio of solar PV projects in Poland.
March 2, 2026
Massachusetts’ state energy efficiency bill contains some positive support for solar energy but falls short on efforts to reduce energy bills, according to US renewables advocacy groups.

Upcoming Events

Solar Media Events
March 24, 2026
Dallas, Texas
Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA
Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain