250MW of green energy corridors commissioned in Andhra Pradesh

August 8, 2016
Facebook
Twitter
LinkedIn
Reddit
Email
Transmission capacity cannot be planned in advance of solar park land acquisition said energy minister Piyush Goyal. Flickr: Tapas Ganesh

India’s green energy corridor plan has seen 250MW of transmission capacity completed around Anantpur with a further 1.25GW due in 2017 in the Andhra Pradesh state.

Speaking in parliament, mines and energy minister Piyush Goyal said Andhra Pradesh was one of the first states to take up the green corridor and solar parks policies. The aim of the corridors is to spread solar and wind power from states rich in renewable resources to areas of high electricity demand and to reduce the risk of curtailment.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Around Anantpur, where there is a 1.5GW solar park named Ananthapuramu, 250MW transmission capacity is already complete under phase I, with 750MW expected in March 2017 under phase II, and 500MW set for September next year under phase III. These completion dates are in line with the expected commissioning dates for the solar power capacity.

Goyal added: “For the other solar parks the government is in dialogue with the Ministry of New and Renewable Energy for procurement of adequate land which will help us implement solar parks.

“As and when the land gets available we will again plant the infrastructure. We cannot plan transmission in advance. There has to be a potential buyer. The buyer has to tend to an agreement with the transmission company to ensure the payment of that transmission line.”

India is soon expected to approve the doubling of its solar park policy plans to 40GW.

Read Next

February 2, 2026
India’s Union Budget 2026-27 reinforces government support for renewables through duty exemptions and infrastructure spending.
January 30, 2026
India Power Corporation Limited has partnered with Bhutan’s Green Energy Power Private Limited to develop a 70MWp solar power plant in Paro, Bhutan
January 29, 2026
PV module defects are increasing as manufacturers struggle to achieve consistent quality through robust bill-of-material and process controls.
January 28, 2026
India’s power system faced growing integration challenges in 2025 as solar curtailment emerged as an early signal of insufficient grid flexibility, according to a new report from energy think tank Ember.
January 23, 2026
MAHAPREIT has issued a tender for a 100MW floating solar project at the Tansa and Modak dams in Thane district, Maharashtra. 
January 22, 2026
Indian rooftop solar provider Fujiyama Power has announced plans to commission its 1GW solar cell manufacturing plant in Dadri, Uttar Pradesh.

Upcoming Events

Solar Media Events
February 3, 2026
London, UK
Upcoming Webinars
February 18, 2026
9am PST / 5pm GMT
Solar Media Events
March 24, 2026
Dallas, Texas
Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA