250MW of green energy corridors commissioned in Andhra Pradesh

August 8, 2016
Facebook
Twitter
LinkedIn
Reddit
Email
Transmission capacity cannot be planned in advance of solar park land acquisition said energy minister Piyush Goyal. Flickr: Tapas Ganesh

India’s green energy corridor plan has seen 250MW of transmission capacity completed around Anantpur with a further 1.25GW due in 2017 in the Andhra Pradesh state.

Speaking in parliament, mines and energy minister Piyush Goyal said Andhra Pradesh was one of the first states to take up the green corridor and solar parks policies. The aim of the corridors is to spread solar and wind power from states rich in renewable resources to areas of high electricity demand and to reduce the risk of curtailment.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Around Anantpur, where there is a 1.5GW solar park named Ananthapuramu, 250MW transmission capacity is already complete under phase I, with 750MW expected in March 2017 under phase II, and 500MW set for September next year under phase III. These completion dates are in line with the expected commissioning dates for the solar power capacity.

Goyal added: “For the other solar parks the government is in dialogue with the Ministry of New and Renewable Energy for procurement of adequate land which will help us implement solar parks.

“As and when the land gets available we will again plant the infrastructure. We cannot plan transmission in advance. There has to be a potential buyer. The buyer has to tend to an agreement with the transmission company to ensure the payment of that transmission line.”

India is soon expected to approve the doubling of its solar park policy plans to 40GW.

Read Next

April 10, 2026
India has become the third-largest country by installed renewable energy capacity, reaching 274.68, with over 150GW of solar PV capacity, according to statistics from the Ministry of New and Renewable Energy (MNRE).
Premium
April 10, 2026
Despite PV’s maturity, a new paper argues that its growing global significance makes ongoing research essential.
April 8, 2026
PV manufacturing capital expenditure is expected to rebound this year, following two years in the doldrums as the industry weathered a global oversupply of modules, new figures show.
Premium
April 8, 2026
After a sharp decline in 2023, PV manufacturing capital expenditure is set to bounce back this year, and not just in China, writes Moustafa Ramadan.
April 7, 2026
Sangam Solar One, a subsidiary of Indian solar PV manufacturer Waaree Energies, has commissioned a 3GW PV module manufacturing facility in Samakhiali, Kutch, Gujarat.
April 7, 2026
According to Ember, solar-plus-storage could supply up to 90% of India’s electricity demand at a levelised cost of electricity (LCOE) of INR5.06/kWh (US$56/MWh).

Upcoming Events

Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA
Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland