Queensland solar operators surprised by curtailment warning, expecting speedy resolution

July 31, 2020
Facebook
Twitter
LinkedIn
Reddit
Email
Genex Power predicts its planned 250MW pumped storage hydro project will solve some of the system strength issues affecting its 50MW Kidston solar park, pictured in the distance. Image: Genex Power.

The operator of a 50MW solar facility in North Queensland at risk of curtailment expects the problem to be resolved in the next few weeks.

Genex Power’s Kidston project was one of nine facilities warned last week by the Australian Energy Market Operator (AEMO) that it may have its output could be cut to zero.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Simon Kidston, co-founder and executive director of Genex Power, told PV Tech that while operators were “caught slightly by surprise” by the notice, the system strength issues at the root of the issue are expected to be resolved in the short term.

System strength issues have arisen following lower-than-normal electricity demand due to COVID-19, as well as maintenance works taking place at other plants.

“I think some of the major coal-fired generators in Queensland have taken this opportunity to do scheduled maintenance of some of those big coal-fired generators,” he said. “And as a result of that, the system strength is not what it normally is.”

As well as Kidston, the eight other solar farms affected are: Clare, Collinsville, Daydream, Hamilton, Hayman, Ross River, Rugby Run and Whitsunday.

According to last week’s AEMO market notice, the limitations on their output are connected to the operations of other hyrdo and coal facilities. New combinations show the solar farms will be permitted to export from 80% to 100% of their power output. If these combinations are not met, they will be cut zero.

Kidston did, however, confirm that Genex’s solar farm had remained fully operational throughout.

Synchronous generation providing grid stability

Syndey-based Genex Power has a development pipeline of up to 770MW of renewable generation and storage projects within its portfolio, underpinned by the Kidston Clean Energy Hub.

Alongside the 50MW solar farm, the hub will consist of a 250MW pumped storage hydro project and an integrated solar project of up to 270MW that are under development, as well as a prospective wind project of up to 150MW under feasibility.

Simon Kidston believes the pumped storage hydro project will be able to solve some of the system strength issues when it becomes operational.

“That plant won't be coming online until the back end of 2023,” he said. “But when it does come online, the strength of the grid in North Queensland will be substantially enhanced.”

He added: “Obviously, we need synchronous generation, in part to maintain that grid stability. So, we've seen pump hydro or hydro more broadly being able to provide that grid stability.”

According to AEMO's quarterly energy dynamics report for Q2, electricity demand was down 2% in the National Electricity Market – which interconnects Queensland, New South Wales, Victoria, South Australia and Tasmania – when compared to Q2 2019. COVID-19 is estimated to have contributed to a 2.1% reduction, while an increase in rooftop PV contributed a further 1.2% decline. In Queensland, the pandemic’s impact is estimated to have reduced demand by 4.8%.

Read Next

November 11, 2025
Hassan Allam Utilities Energy Platform and Infinity Power have signed agreements to develop two renewable energy projects in the country. 
November 10, 2025
The Australian Renewable Energy Agency (ARENA) will invest up to AU$45 million (US$29 million) in Fortescue's Solar Innovation Hub in the Pilbara region of Western Australia.
November 10, 2025
EnergyCo has shortlisted three consortia to build and operate the transmission network for the New England Renewable Energy Zone (REZ).
November 10, 2025
The Australian government has approved the 300MW Dunmore solar-plus-storage project near Toowoomba, Queensland, completing the environmental assessment process in just 19 days.
November 7, 2025
Apple has signed a power purchase agreement (PPA) with Danish developer European Energy for renewable electricity from the 108MW Lancaster solar park in Victoria, Australia.
November 7, 2025
Australian energy retailer Flow Power has secured an offtake agreement from the 400MW Stubbo Solar project in New South Wales to underpin the launch of its Flow Home residential energy service in the state.

Subscribe to Newsletter

Upcoming Events

Upcoming Webinars
November 12, 2025
10am PST / 1pm EST
Solar Media Events
November 25, 2025
Warsaw, Poland
Solar Media Events
December 2, 2025
Málaga, Spain
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 24, 2026
Lisbon, Portugal