SECI tenders 750MW of solar in Rajasthan

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn
Share on reddit
Reddit
Share on email
Email
Credit: REC

The Solar Energy Corporation of India (SECI) has issued a tender for the development of 750MW of grid-connected solar projects in Rajasthan.

The developers will be responsible for land acquisition, transmission and grid-connection as well as long-term open access. They shall set up the PV projects on a build, own and operate (BOO) basis.

SECI will sign power purchase agreements (PPAs) with successful bidders for a period of 25 years at a maximum tariff of INR2.93/kWh.

Projects will have a minimum capacity of 10MW and a maximum of the full 750MW, with project allocation going up in increments of 10MW at a time.

Any excess generation over and above 10% of the declared annual capacity utilisation factor (CUF) will be purchased by SECI at a fixed tariff of 75% of the PPA tariff, provided SECI is able to find a buyer for this excess generation.

Developers of projects of up to 240MW in size will have 21 months from the date of signing the PPA to complete the projects, following a recent Ministry of Power solar procurement guidelines amendment that allowed procurers to extend the deadline for commissioning projects. In SECI's tender, projects of 250MW and above in capacity will have 24 months from the PPA signing date to be completed.

The bid submission deadline is 14 September this year.

Cost versus safeguard

SECI recently cancelled 2.4GW of auctioned projects under its 3GW Interstate Transmission System (ISTS)-connected solar tender, accepting only the 600MW won by Acme Solar due to its significantly lower bid of INR2.44/kWh. Media reports said that all other winning developers had refused government requests for them to lower their original winning bids.

It is unclear exactly how the imposition of new safeguard duty will impact any bidding in the case of a re-tender, but it will certainly be an extra factor pushing bids higher than before due to the extra costs on importing modules.

Meanwhile, bids in SECI’s 200MW Odisha tender, for which an auction was held the day after the safeguard duty announcement, came in at between INR 2.79-3.20/kWh. These prices were seen as fairly unaffected by the safeguard announcement, although the tender does explicitly include a pass-through clause for a change-in-law.

Results were as follows:

Developer Capacity (MW) Tariff (INR/kWh)
Aditya Birla 75 2.79
Eden Renewable Varenne 50 3.19
Acme 30 3.20
Sukhbir Agro 25 3.19
Gupta Power Infrastructure 20 3.19

Read Next

July 30, 2021
First Solar has unveiled plans to construct a 3.3GWdc module assembly facility in India, bolstering its manufacturing footprint outside of the US.
July 20, 2021
It is “unhealthy” for China to dominate solar manufacturing and production bases outside of the country are necessary to reduce the risk of supply chain disruptions, an Indian government official has said.
July 20, 2021
Vikram Solar has completed a new 1.3GW solar module manufacturing facility in Tamil Nadu, India, taking its total manufacturing output to 2.5GW.
July 13, 2021
Solar PV capacity in Asia Pacific could triple to 1,500GW by 2030, with China driving deployment and Indonesia set to be the region’s fastest-growing market, according to Wood Mackenzie.
June 28, 2021
Module and cell manufacturers in India will expand their production capabilities by 13.75GW for modules and 6.9GW for solar cells, according to research by JMK Research and Analytics
June 25, 2021
Indian conglomerate Reliance Industries will construct an integrated PV module factory and look to enable more than 100GW of solar by 2030 as part of a US$10.1 billion clean energy plan.

Subscribe to Newsletter

Upcoming Events

Upcoming Webinars
August 19, 2021
At 9am (PT) | 6pm (CEST)
Solar Media Events
August 25, 2021
Solar Media Events
October 6, 2021
Solar Media Events
October 19, 2021
BRISTOL, UK