SECI tenders 750MW of solar in Rajasthan

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn
Share on reddit
Reddit
Share on email
Email
Credit: REC

The Solar Energy Corporation of India (SECI) has issued a tender for the development of 750MW of grid-connected solar projects in Rajasthan.

The developers will be responsible for land acquisition, transmission and grid-connection as well as long-term open access. They shall set up the PV projects on a build, own and operate (BOO) basis.

SECI will sign power purchase agreements (PPAs) with successful bidders for a period of 25 years at a maximum tariff of INR2.93/kWh.

Projects will have a minimum capacity of 10MW and a maximum of the full 750MW, with project allocation going up in increments of 10MW at a time.

Any excess generation over and above 10% of the declared annual capacity utilisation factor (CUF) will be purchased by SECI at a fixed tariff of 75% of the PPA tariff, provided SECI is able to find a buyer for this excess generation.

Developers of projects of up to 240MW in size will have 21 months from the date of signing the PPA to complete the projects, following a recent Ministry of Power solar procurement guidelines amendment that allowed procurers to extend the deadline for commissioning projects. In SECI's tender, projects of 250MW and above in capacity will have 24 months from the PPA signing date to be completed.

The bid submission deadline is 14 September this year.

Cost versus safeguard

SECI recently cancelled 2.4GW of auctioned projects under its 3GW Interstate Transmission System (ISTS)-connected solar tender, accepting only the 600MW won by Acme Solar due to its significantly lower bid of INR2.44/kWh. Media reports said that all other winning developers had refused government requests for them to lower their original winning bids.

It is unclear exactly how the imposition of new safeguard duty will impact any bidding in the case of a re-tender, but it will certainly be an extra factor pushing bids higher than before due to the extra costs on importing modules.

Meanwhile, bids in SECI’s 200MW Odisha tender, for which an auction was held the day after the safeguard duty announcement, came in at between INR 2.79-3.20/kWh. These prices were seen as fairly unaffected by the safeguard announcement, although the tender does explicitly include a pass-through clause for a change-in-law.

Results were as follows:

Developer Capacity (MW) Tariff (INR/kWh)
Aditya Birla 75 2.79
Eden Renewable Varenne 50 3.19
Acme 30 3.20
Sukhbir Agro 25 3.19
Gupta Power Infrastructure 20 3.19

Read Next

September 20, 2021
A subsidiary of Indian utility Tata Power has received a letter of intent to set up a 250MW grid-connected solar project in the state of Maharashtra.
September 13, 2021
The Indian state of Tamil Nadu is planning to develop 4GW of additional solar projects as well as new battery energy storage systems, according to local media.
September 10, 2021
Independent power producer ReNew Power has commissioned a 250MW portion of a 300MW solar plant in the Indian state of Rajasthan.
September 6, 2021
India-based renewables developer Adani Green Energy has raised US$750 million through a green bond offer, securing the debt and equity needed to reach a 25GW renewables target.
September 3, 2021
Uzbekistan has started the request for qualification stage for a solar tender that will support three projects totalling up to 500MW, including one paired with a battery energy storage system.
September 2, 2021
Reliance Industries is close to acquiring solar module manufacturer REC Group, according to media reports in India, as part of the conglomerate’s expansion into the renewable energy sector.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
October 6, 2021
Solar Media Events
October 19, 2021
BRISTOL, UK
Solar Media Events
December 1, 2021