Southern region to lead India in grid integration of renewable energy - Bridge to India

By Bridge to India
Facebook
Twitter
LinkedIn
Reddit
Email
Enhanced transmission connectivity as well as rapid renewable energy deployment has helped south India in considerably reducing its power deficit. Credit: Renew Power

India’s southern region comprising Andhra Pradesh, Telangana, Karnataka, Tamil Nadu and Kerala accounts for 25% of national power consumption but 45% of the country’s total wind and solar power capacity. Penetration of variable wind and solar energy, defined as generation from both these sources as a percentage of electricity consumption, in the southern region was 9% in 2016-17 as against the national average of 5%. Such a high rate of penetration raises concerns regarding management of the grid and can result in high grid curtailment rate. South India represents a test case for the country in terms of integrating variable renewable energy into the grid.

  • Increased renewable energy deployment is changing the energy landscape in the southern region and raises concerns regarding grid stability and power curtailment;
  • While strides have been made in enhancing transmission connectivity, a lot still needs to be done to enhance grid flexibility and develop ancillary services market;
  • Lessons should also be learnt from successful international experiences in allowing high renewable energy grid penetration;

Enhanced transmission connectivity as well as rapid renewable energy deployment has helped south India in considerably reducing its power deficit from 7.3% in 2013-14 to only 0.2% in 2016-17. But another 9GW of wind and solar energy capacity is estimated to be under development. Tamil Nadu is already facing the brunt of such high renewables generation with wind curtailment rates as high as 33% in 2013-14.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Significant steps are being taken to enhance transmission connectivity under the government’s green energy corridor scheme. Work has already commenced on an 1,800km ultra-high voltage transmission link between central and southern India. However, little attention is being paid to other equally important and effective solutions including more accurate generation and load forecasting, ancillary services development (for frequency and voltage stability) and improved flexibility of conventional power plants. For instance, Karnataka is the only southern state to have finalised a regulation on forecasting and scheduling of power. The region is also a laggard in development of an ancillary services market. In the first six months of implementation of regulatory reserve ancillary services (April-September 2016), only 6% of the total energy dispatched under “regulation up” service came from southern region.  

Lessons should be learnt from other countries including the USA and Germany, which have similar or higher renewable energy penetration levels. The Electric Reliability Council of Texas (ERCOT) in the USA was successful in reducing the wind curtailment rate from 17% in 2009 to 0.5% in 2014 in its region despite the share of wind power generation increasing from 6.2% to 10.6% in this period. It did so by building more transmission capacity, reducing scheduling time intervals from 15 minutes to 5 minutes, introducing fast frequency response reserves for instantaneous increase/decrease in power output and various demand response programmes along with rapid deployment of smart meters. Germany has also been successful in keeping curtailment rates below 4%, despite having a renewable energy penetration level of as high as 30%, mainly because of adoption of a variety of market-based mechanisms to enhance grid flexibility and provision of ancillary services. For instance, during periods of excess power supply, the German power trading market fixes a negative price for inflexible power units. Moreover, through retrofits to existing coal power plants, Germany has also made thermal generation more flexible to respond to changes in renewable energy generation.

In order for India to support ongoing renewable energy deployment, it is essential to learn from international as well as domestic experience and make urgent changes to the power system.

22 October 2026
India Expo Mart, Greater Noida
Whether you're looking for new technologies, trusted partners, or fresh business opportunities, you'll find them at the 19th Renewable Energy India Expo 2026. Join 55,000+ industry professionals and 1,000+ exhibiting brands across 14 halls featuring solar, bioenergy, battery storage, and the Germany Pavilion. It's where the clean energy sector comes together to exchange ideas, build partnerships, and drive business forward.
2 February 2027
London, UK
Returning in 2027 for its 14th edition, Solar & Storage Finance Europe will bring together the brightest minds representing funds, banks, developers, utilities, government and industry across Europe and the UK on a programme that is solutions-focused from top to tail. The event is designed to enable leaders at the forefront of solar and storage investment and deployment in Europe to scale, learn and land themselves industry defining partnerships.

Read Next

August 21, 2026
Vikram Solar plans a 9GW wafer and ingot plant at its recently inaugurated 6GW Tamil Nadu module facility.
Premium
August 21, 2026
PV Tech Premium speaks with United Solar about the challenges of building polysilicon capacity outside of China and catering to the US and Indian markets.
August 21, 2026
SA Power Networks will run its annual test of the state's rooftop solar curtailment system on 25 August in South Australia.
August 20, 2026
Freyr Energy has launched a range of single-phase solar PV inverters with 3kW and 5kW models using silicon carbide (SiC) technology.
August 20, 2026
GameChange Energy has broken ground on a major expansion of its transformer manufacturing facility in Mumbai, India, as the company continues to evolve beyond its solar tracker roots into the provision of critical power infrastructure.
August 20, 2026
French energy major Engie has signed a deal to supply power from a 61MW solar PV project to a data centre in Irving, Texas.

Upcoming Events

Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
February 2, 2027
London, UK
Solar Media Events
April 20, 2027
Istanbul, Türkiye