UPDATED: Winning bids in a 550MW solar auction in Uttar Pradesh, India, have come out between INR 3.02-3.08/kWh (US$0.0429-0.0437), a notable drop from 3.17-3.23 rupees in its most recent 500MW auction in October.

Uttar Pradesh New and Renewable Energy Development Agency (UPNEDA) saw the lowest bid come in from India's largest distribution company NTPC, which has only recently tried its hand in PV auctions in India.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The results were as follows:

Bidder Tariff (INR/kWh) Capacity (MW)
NTPC 3.02 85
Bastille Solar (EDF) 3.04 70
Bastille Solar 3.07 70
Giriraj Renewables (Avaada) 3.07 100
Mahoba Solar (Adani) 3.07 50
Tata Power Renewable Energy 3.07 50
Jakson Power 3.07 50
Tata Power Renewable Energy 3.08 50
Mahoba Solar 3.08 25 (bid for 50)

Other bidders that missed out on capacity included Vijay Printing Press and Sukhbir Agro, while Mahoba Solar (Adani) put in several other unsuccessful bids.

Vinay Rustagi, managing director of Bridge to India, told PV Tech: “The list of winners is very similar to the last tender just two months ago. Most of these are Indian developers apart from EDF. The fall can be largely explained by a continued fall in the module prices which are expected to remain soft going well into the next year and so the tariff fall is understandable.

“UP has one of the worst rated Discoms in the country, but what we increasingly see is that many of the developers, particularly the Indian developers, seem to be quite happy with the offtake risk of Uttar Pradesh and it's hard to tell whether it is just a case of getting comfortable with the offtake risk or whether, because the pipeline is being so erratic and building new capacities is becoming more difficult, the developers have just decided that even if they can bag some capacity in the UP tender, so be it.”

In November, UPNEDA issued a request for selection (RfP) for a 200MW solar park to be awarded through competitive bidding.

Updated to include comment from Bridge to India.

Read Next

February 2, 2026
India’s Union Budget 2026-27 reinforces government support for renewables through duty exemptions and infrastructure spending.
January 30, 2026
India Power Corporation Limited has partnered with Bhutan’s Green Energy Power Private Limited to develop a 70MWp solar power plant in Paro, Bhutan
January 29, 2026
PV module defects are increasing as manufacturers struggle to achieve consistent quality through robust bill-of-material and process controls.
January 28, 2026
India’s power system faced growing integration challenges in 2025 as solar curtailment emerged as an early signal of insufficient grid flexibility, according to a new report from energy think tank Ember.
January 23, 2026
MAHAPREIT has issued a tender for a 100MW floating solar project at the Tansa and Modak dams in Thane district, Maharashtra. 
January 22, 2026
Indian rooftop solar provider Fujiyama Power has announced plans to commission its 1GW solar cell manufacturing plant in Dadri, Uttar Pradesh.

Upcoming Events

Solar Media Events
February 3, 2026
London, UK
Upcoming Webinars
February 18, 2026
9am PST / 5pm GMT
Solar Media Events
March 24, 2026
Dallas, Texas
Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA