Application deadline for Thailand’s 300MW hybrid renewables PPA scheme draws near

Facebook
Twitter
LinkedIn
Reddit
Email
The PPAs require a continuous baseline level of production not previously seen in stand-alone solar or wind farms. Credit: Sonnedix

Submissions for Thailand’s first 300MW hybrid PPA scheme, which encourages use of energy storage to supplement renewable energy generation, are due by 20 October.

Earlier this year, Thailand’s Ministry of Energy announced the hybrid scheme and the Energy Regulatory Commission (ERC) brought out details of the related 20-year power purchase agreements (PPAs) over the summer.

Franck Constant, president of renewables and storage investment platform Constant Energy, told PV Tech that the regulator has been trying to promote the development of energy storage batteries and the PPA requirement of having a fixed output during the day opens up an opportunity for renewable energy developers to add energy storage capabilities.

In a briefing note, international law firm Watson Farley & Williams stated: “Thailand’s previous renewable energy PPAs were ‘nonfirm’ and accommodated the delivery of electricity below the installed capacity of the power plant. However, the new hybrid PPAs will be ‘firm’ in order to reduce the variation in intermittent energy sources, and will require a continuous baseline level of production not previously seen in stand-alone solar or wind farms.”

Watson Farley & Williams explained that the ‘firm’ element of the PPAs requires the power producer to deliver between 98% and 102% of the PPA capacity during peak periods, which in Thailand is the daytime period between 9am and 10pm on weekdays. The PPA then limits power output at other times to 66.3% of the PPA capacity.

Projects must be between 10-50MW in size. The law firm suggested that the 65% baseline requirements could be achieved through biomass, biogas and refuse-derived fuel, while solar, wind and small hydro combined with storage batteries could bring generation up to 100% during the peak daytime periods.

Watson Farley & Williams also noted: “Fossil fuels (such as natural gas) can only be used to the extent required in the startup process of a power generator, but coal is not permitted in any circumstances.”

The scheme comes with a feed-in tariff (FiT) for renewables of THB3.66/kWh (US$0.111), which is split between a FiT for the fixed tariff component of THB1.81/kWh and a FiT for the variable tariff component of THB1.85/kWh.

The 300MW are mostly located in the south, north and north-eastern regions: 

Region target allocation (MW)
Bangkok 15
Central Region (Excluding Bangkok) 20
Western 20
Eastern 20
Northern 65
North Eastern 60
Southern (Excluding Phuket and Samui) 65
Phuket 20
Samui 15

Projects will be awarded via a competitive bidding process, with applicants required to specify a percentage discount rate of the FiT for the fixed tariff component. Projects are due to be commissioned between January 2020 and the end of 2021.

To date, energy storage has made little progress in Thailand and while its large-scale PV progress rests largely in a complicated cooperative scheme, its corporate PPA sector is thriving.

Read Next

August 9, 2022
The Public Service Commission of the District of Columbia (DCPSC) has approved a 15-year power purchase agreement (PPA) with renewables developer Invenergy for 73MW of solar power to meet a 5% renewables target for district’s default electricity supply.
August 8, 2022
Energy technology company AES Corporation is still on track to reach its target of 4.5-5.5GW in long-term renewables and energy storage contracts in 2022, having already signed 1,618MW in the year to date, according the firm’s Q2 financial report.
August 3, 2022
Tata Power subsidiary Tata Power Green Energy has commissioned a 225MW hybrid wind and solar project in the Indian solar hotbed state of Rajasthan.
July 28, 2022
Manufacturing support for solar components and clean energy tax credits are included in a proposed US budget reconciliation bill from Senate Democrats that proponents have said features the biggest climate and renewables investment in the country’s history.
July 27, 2022
US utility-scale solar installations in Q2 2022 were down 53% year-on-year as policy headwinds and trade issues impacted development and increased the backlog of delayed projects, a new report has revealed.
July 26, 2022
Solar developer Lightsource bp has signed a 15-year power purchase agreement (PPA) with energy trader América Energia for an under-construction PV plant in the Brazilian state of Ceará.

Subscribe to Newsletter

Upcoming Events

Upcoming Webinars
September 7, 2022
15:30 AEST (UTC +10)
Solar Media Events
September 14, 2022
London
Solar Media Events
October 4, 2022
New York, USA
Solar Media Events
October 11, 2022
Virtual event