Maoneng, Decmil break ground on 255MW New South Wales solar project

Facebook
Twitter
LinkedIn
Reddit
Email
Maoneng is also now preparing another 500MW of solar to be commissioned in line with the proposed SA/NSW interconnector, together with additional energy storage. Credit: Maoneng Australia

EPC contractor Decmil has broken ground on the 255MW Sunraysia solar plant in Balranald, New South Wales, Australia, which is being developed by Maoneng Australia.

Construction on the plant will require 350-400 workers, with the installation of more than 755,000 JinkoSolar PV panels mounted onto single-axis trackers from NEXTracker, more than 4,000km of cables and 100,000 piles over 800 Hectares. A large-scale grid-connected energy storage project, named Sunraysia Emporium, will be located adjacent to the Sunraysia Solar Farm.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The PV project is expected to generate approximately 529GWh of energy per year when commissioned; which is the equivalent to powering up to 50,000 households.

The solar farm is connected to a 33/220kV substation co-located on-site where the energy is transferred to the Transgrid 220kV Balranald Substation. From there the energy is then transferred either towards Buronga/VIC or Darlington Point/NSW. As part of the works, approximately 400km of new fibre optic cable will be installed between the Buronga and Darlington Point substations to improve communication and control of the solar farm.

The project is supported by two Power Purchase Agreements (PPAs) under which UNSW Sydney and AGL Energy (AGL) will purchase energy over 15 years. It reached financial close with John Laing in October last year.

“As a responsible renewable energy developer, we are cognisant of the impact which renewable energy has, both good and bad. To improve the reliability and to minimise both the technical and commercial impact of our developments moving forward, we aim to implement energy storage systems capable of time-shifting large amounts of energy throughout the day. Only by doing this, as a matter of best practice, will we be able to transition towards a 100% renewable energy future,” said Qiao Nan Han, VP of Maoneng Group.

“Sunraysia is strategically placed to service multiple states and territories given its proximity to the proposed interconnectors and the main charging route for the Snowy 2.0. AEMO’s ISP (Integrated System Plan) looks at various scenarios including the development of a large Renewable Energy Zone here at Balranald. We are excited to be part of this moving feast and welcome the challenges and responsibilities which come with these developments,” Nan Han added.

Maoneng is also now preparing another 500MW of solar to be commissioned in line with the proposed SA/NSW interconnector, together with additional energy storage.

Australia is a global frontrunner in large-scale solar-plus-storage projects, with regular project announcements over the last year.

Read Next

Premium
May 11, 2026
In this interview, UNSW's Yansong warns the solar industry will exhaust global silver reserves in five years unless commercial-scale recycling infrastructure is developed.
May 11, 2026
Yindjibarndi Energy Corporation (YEC) has reached financial close on the 150MW Jinbi solar PV power plant in Western Australia's Pilbara region and signed a 30-year power purchase agreement (PPA) with mining giant Rio Tinto.
May 8, 2026
Australia's utility-scale solar sector must halve generation costs to around AU$25-30/MWh (US$18-22/MWh) to unlock a pipeline of projects capable of delivering the 10GW of annual capacity additions needed for decarbonisation, according to the Australian Renewable Energy Agency (ARENA).
May 7, 2026
Neoen has brought its 440MWp Culcairn Solar Farm online in NSW, marking the completion of the company's second-largest solar asset globally.
May 7, 2026
Australia’s New South Wales government has introduced legislation to accelerate the delivery of renewable energy infrastructure as the state's coal-fired power stations prepare to exit the system.
May 6, 2026
The Australian government has announced the results of CIS Tenders 5 and 6 for Western Australia, awarding contracts to 10 projects.

Upcoming Events

Solar Media Events
May 20, 2026
Porto, Portugal
Upcoming Webinars
May 27, 2026
9am BST / 10am CEST
Media Partners, Solar Media Events
June 3, 2026
National Exhibition and Convention Center (Shanghai)
Solar Media Events
June 16, 2026
Napa, USA
Media Partners, Solar Media Events
August 25, 2026
São Paulo, Brazil