New guidelines for Indian solar power procurement to bring confidence to the sector

By Bridge to India, a leading consultancy in India's renewables market
Facebook
Twitter
LinkedIn
Reddit
Email
The Bridge to India team Credit: SunEdison

The Ministry of Power has issued new “Guidelines for tariff-based competitive bidding process” for solar power plants. The guidelines shall be applicable to all projects equal to or greater than 5MW for supplying power directly/indirectly to distribution comapnies (Discoms) subject to approval from the respective central or state regulator. For the first time in the sector, the government also proposes to issue standard bid documents including request for selection, PPA and other ancillary documents.

The proposed changes, while still not going far enough, are a major improvement on the current framework. Introduction of standard documentation, in particular, will be of major help to developers and investors. Significant changes are discussed below:

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Readiness of project site:

The guidelines specify strict timelines for completion of land acquisition, transmission connectivity and other approvals in a timebound manner to avoid project delays. If the power purchaser retains responsibility for these in the form of a solar park, then it must ensure that: i) at the time of bidding, 100% of land is identified and proof of in-principle availability of 25% of land is in place; and ii) within one month of PPA signing, 90% of land is acquired and balance 10% is acquired in the next two months. All statutory clearances and transmission connectivity feasibility should be available prior to PPA signing.

If there is no solar park available, the developer must: i) have identified 100% of land requirement at the time of bid submission and complete full land acquisition within 7 months from the date of PPA signing. It must also ensure that environment/forest clearances, approval for water and transmission technical feasibility are available.

Payment security mechanism:

In addition to a letter of credit for one-month billing, the power purchaser (Discom or an intermediary buyer such as NTPC/SECI) needs to establish a payment security fund equivalent to three-month billing amount. This is a major improvement over current practice and will help in reducing Discom payment risk perception.

Where Discoms are buying power through an intermediary entity such as NTPC/SECI, they are required to procure a state government guarantee in favour of NTPC/SECI if a tripartite agreement between the respective state government, Reserve Bank of India and the central government is not in place.

Compensation for offtake constraints:

The guidelines recognise that grid backdowns/curtailment are becoming a bigger problem for the sector and seek to provide compensation to developers for the same. In the event of generation loss due to evacuation infrastructure not being ready or being unavailable for more than 50 hours in a year, the developers are allowed to sell equivalent amount of extra power over subsequent three years. In the event of back-down requests from Discoms, 50% of revenue shortfall will be met by the Discom. However, there is no compensation for any backdowns due to grid instability or safety reasons.

These clauses are a positive step but they still do not provide sufficient protection to the developers from curtailment or back-down risks.

Termination compensation:

It is unbelievable that most solar PPAs in India today do not have any provision for termination compensation for a power purchase default. The new guidelines specify that the developer can terminate the PPA in case of a power purchaser default and seek compensation equivalent to total debt outstanding plus 150% of adjusted equity, or six months billing amount, whichever is lesser. The introduction of this clause will serve as a major deterrent against default and protect the developers from Discoms seeking to unilaterally cancel or re-negotiate PPAs.

Lender substitution rights:

The new standard PPA will allow substitution if the developer defaults on payments to its lender(s). Previously, substitution was permissible only if the developer had defaulted on its PPA obligations.

These changes have come after extensive consultations and aim to protect developer and investor-lender interests. As we saw with the recent Rewa tender, improved contractual documentation and risk allocation can provide more confidence to the sector and lead to a win-win arrangement for all parties.

Read Next

October 6, 2025
Indian infrastructure company focused on rooftop and ground-based solar power installations, PVV Infra has secured solar power orders worth INR7.9 billion (US$90 million) through two of its subsidiaries. 
October 6, 2025
Indian solar developer ACME Group has established a new subsidiary to manage its renewable equipment manufacturing business, under which it is planning to scale production of TOPCon PV modules.
October 6, 2025
Rajasthan government will develop 500MW/2,000MWh of standalone battery energy storage systems (BESS) with a four-hour single-cycle configuration and extended operational life.
October 2, 2025
The Indian solar industry has 86GW and 182GW of solar cell and module manufacturing capacity, respectively, expected to be commissioned by 2027.
October 2, 2025
The Indian Department of Commerce has launched an antidumping investigation on solar encapsulants originating or exported from South Korea, Vietnam and Thailand.
September 29, 2025
Indian solar manufacturer Waaree has said it does not expect to pay additional duties on its solar cell imports to the US, following the start of an antidumping and countervailing duty (AD/CVD) investigation by the US Customs and Border Patrol (CBP).

Subscribe to Newsletter

Upcoming Events

Solar Media Events
October 7, 2025
Manila, Philippines
Solar Media Events
October 7, 2025
San Francisco Bay Area, USA
Solar Media Events
October 21, 2025
New York, USA
Solar Media Events
November 25, 2025
Warsaw, Poland