Major Chinese module manufacturers call for government intervention over ‘out of control’ glass prices

November 3, 2020
Facebook
Twitter
LinkedIn
Reddit
Email
The ASP of solar glass has more than doubled since July as a result of shortages. Image: Frounhofer.

Major module manufacturers in China have called on the country’s government to intervene and ease solar-grade glass shortages they have said are “out of control”.

In a joint statement issued today, Canadian Solar, Risen Energy, JA Solar, JinkoSolar, LONGi and Trina Solar, as well as others, have issued a list of potential remedies for the Communist Party of China to consider as it puts together its 14th Five-Year Plan, due to be unveiled early next year.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The calls come after the industry has witnessed the average selling price (ASP) of solar-grade 3.2mm glass more than double since July, caused by a “serious shortage” which has “critically affected” production and delivery of solar PV modules in recent months, the companies said.

The statement argues that following a turbulent start to the year, with the COVID-19 pandemic impacting the entire solar value chain, demand for modules has exploded, and China alone is expected to install as much as 29GW in the second half of 2020, driven at least partly by grid connection deadlines.

Demand for modules has placed greater strain on the industry’s supply chain, and glass in particular is in high demand.

“[The] PV industry has become China’s business card, and the shortage of glass has made it difficult for many overseas orders to be delivered, and this undermines not just the reputation of enterprises, but even the country itself,” the statement reads.

The six majors to have co-signed the letter have stated they are now collaborating and coordinating resources in order to guarantee supply of glass, but has called upon relevant state departments in China to intervene with glass production capacity having been “seriously left behind” as module manufacturers have hit the accelerator on capacity expansion plans.

“The total supply of modules is insufficient, and PV module companies have already experienced large-scale delivery delays,” the companies have said.

Most of the remedies are targeted at relaxing penalties and other losses associated with utility-scale projects missing grid connection deadlines as a result of module supply shortages. The companies have urged state departments to consider introducing policies to “cool down the rush for installation” towards the year’s end, and guide the progress of projects affected by supply chain constraints.

The statement also calls for upstream glass manufacturers to “take the initiative and work together” with downstream module companies to guarantee supply, while it also urges that policy-making departments in China to consider the “urgent situation” facing solar development and to loosen any restrictions on glass production capacity expansions that may be affected by measures within China’s forthcoming Five-Year Plan.

 

More to follow…

Read Next

November 17, 2025
Jakson Group has started Phase 1 construction of its 6GW integrated solar ingot, wafer, cell and module manufacturing facility at Maksi, Madhya Pradesh.
November 17, 2025
India’s race to 500GW is being slowed by critical grid bottlenecks, NTPC PMI’s Abhinav Jindal told PV Tech.
November 17, 2025
Saatvik Green Energy, through its subsidiary Saatvik Solar Industries, has secured solar PV module orders worth INR1.77 billion (US$19.9 million). 
November 17, 2025
US solar module manufacturer First Solar will build a new production facility in the state of South Carolina, which will bring its US nameplate manufacturing capacity to 17.7GW by 2027.
Premium
November 17, 2025
PV Talk: India’s race to 500GW of clean energy is being slowed by critical bottlenecks. NTPC PMI’s deputy general manager Abhinav Jindal tells Shreeyashi Ojha what steps India must urgently take to stay on track with its 2030 targets.
November 14, 2025
Lightsource bp has started construction on its 330MWp Valle 3 and 4 project in Wamba, Valladolid, in the Castilla y Leon region of Spain. 

Upcoming Events

Solar Media Events
November 25, 2025
Warsaw, Poland
Solar Media Events
December 2, 2025
Málaga, Spain
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 24, 2026
Lisbon, Portugal
Solar Media Events
June 16, 2026
Napa, USA