Netherlands to restrict grid linking requests to alleviate congestion

Facebook
Twitter
LinkedIn
Reddit
Email
Image credit: Paul van de Velde / Flickr

A controversial move by network operators has laid bare once more the Netherlands’ issues with grid overcrowding, with PV projects now set for connection delays in under-pressure areas.

Holland Solar joined other energy sector associations this week as they slammed the decision by network operators Liander and Enexis to freeze the linking of new projects in congested zones.

This article requires Premium SubscriptionBasic (FREE) Subscription

Unlock unlimited access for 12 whole months of distinctive global analysis

Photovoltaics International is now included.

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Unlimited digital access to the PV Tech Power journal catalogue
  • Unlimited digital access to the Photovoltaics International journal catalogue
  • Access to more than 1,000 technical papers
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

In a statement alongside trade bodies for wind power (NWEA) and the broader energy sector (Energie-Nederland), Holland Solar acknowledged the pressure building over the Dutch grid.

“It has been clear for some time that in a number of areas in the Netherlands the transmission capacity may be too tight for connecting new sustainable energy projects,” their statement said.

The document laid congestion issues at the network operators’ door, however. The operators, Holland Solar claimed, have failed to fully anticipate how quickly clean energy would grow.

According to the association trio, the decision by Liander and Enexis to close off areas for grid connection must be probed by regulators and other third parties to ensure it is substantiated.

“The sudden closure… is far-reaching and means that many sustainable project developers, often also small-scale solar and rooftop projects, are left empty-handed,” the trade bodies said.

PV under political spotlight in overcrowded state

The controversy opens yet another front for Dutch PV, which must contend with the country’s distinctive mix of scarce land, relatively weak power prices and opposition from campaigners.

MPs in the small state – one of Europe’s most densely populated – were close to enacting a temporary permit ban for new ground-mounted PV in May, choosing to call off the proposal later.

Solar was then singled out by the government in July, when it acted to make it compulsory for clean energy subsidy applicants to secure a preliminary go-ahead from network operators.

Network operators have also sought to make their case for restricting clean energy project connections, at least until grid upgrades have had the time to materialise.

Announcing its temporary system of “congestion management”, Liander said large-scale solar parks, data centres and others vying for grid space must wait until network expansion kicks in.

According to the operator, grid upgrades need time and face a “chronic shortage” of technicians. “The Dutch system is not geared to these rapid and impactful developments,” Liander argued.

Despite its grid-related headaches, Dutch PV has lately witnessed utility-scale milestones and has majorly benefited from successive rounds of the SDE subsidy programme.

The prospects and challenges of solar's new era in Europe and beyond will take centre stage at Solar Media's Solar Finance & Investment Europe (London, 5-6 February) and Large Scale Solar Europe 2020 (Lisbon, on 31 March-1 April 2020).

Read Next

Subscribe to Newsletter

Upcoming Events

Solar Media Events
April 10, 2024
Dallas, Texas USA
Solar Media Events
April 17, 2024
Lisbon, Portugal
Solar Media Events
May 1, 2024
Dallas, Texas
Solar Media Events
May 21, 2024
Napa, USA