Origis Energy commissions 150MW Golden Triangle II solar-plus-storage project

May 29, 2024
Facebook
Twitter
LinkedIn
Reddit
Email
origis energy
Origis Energy’s Mississippi portfolio will have a combined capacity of 550MW. Image: Origis Energy

US renewable energy developer Origis Energy has commissioned a 150MW solar-plus-storage project in the US state of Mississippi.

The project, Golden Triangle II, includes a 50MW battery energy storage system (BESS), and started producing electricity on 21 May. The project is part of a three-facility portfolio, including the Golden Triangle I project and the Optimist project, which each have 200MW of solar generation capacity alongside 50MW of BESS capacity. This is the largest storage portfolio under construction in Mississippi, and Origis expects to commission all three projects next year.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“Solar energy enhances Mississippi’s economic competitiveness, and Origis is removing limits to a cleaner, brighter future by building the region’s clean-energy infrastructure,” said Origis chief commercial and procurement officer Johan Vanhee. “Golden Triangle II is the first step in fostering a zero-carbon economy across the state that supports our nation’s economic and energy security goals.”

Origis signed a power purchase agreement (PPA) to sell power generated at the projects to the Tennessee Valley Authority (TVA), a utility, at what the companies called “competitive rates”. TVA will use the power to meet the energy demand of its large industrial customers, including Meta, which is among the leaders in clean power acquisition in the US, having signed a PPA with Pine Gate Renewables earlier this week.

TVA has announced plans to expand its renewable energy portfolio in recent years, aiming to add 10GW of new solar generation capacity by 2035, up from 2.4GW in operation currently. The TVA operates predominantly in Mississippi, which has one of the smaller solar sectors in the US, with the Solar Energy Industries Association (SEIA) expecting developers to add just 2.2GW of new capacity to the Mississippi solar sector in the next five years, 24th among the states.

In January, Origis announced that it had received US$317 million in funding from J.P. Morgan to support the development of both the Golden Triangle II project, and the 200MW Escalante Solar project in New Mexico.

Read Next

November 21, 2025
BNZ has started commercial operations at a portfolio of solar PV projects in Spain with a combined capacity of 150MW.
November 21, 2025
CPS Energy has issued a request for proposals (RFP) to acquire 600MW of new solar capacity through power purchase agreements (PPA).
November 20, 2025
Climate Fund Managers (CFM) has started commercial operations at the 26.4MW Pétalo del Norte I solar PV project in Colombia.
November 18, 2025
Tata Power Renewable Energy has commissioned a 300MW solar PV project for Indian hydropower company NHPC in Rajasthan. 
November 18, 2025
JinkoSolar shipped just over 20GW of solar PV modules in the third quarter of this year, down sequentially from the previous quarter.
November 14, 2025
Developer rPlus Energies has acquired two solar and storage projects with the total capacity of 900MW in Ada County, Idaho.

Upcoming Events

Solar Media Events
November 25, 2025
Warsaw, Poland
Solar Media Events
December 2, 2025
Málaga, Spain
Upcoming Webinars
December 4, 2025
2pm GMT / 3pm CET
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 24, 2026
Lisbon, Portugal