Origis Energy commissions 150MW Golden Triangle II solar-plus-storage project

May 29, 2024
Facebook
Twitter
LinkedIn
Reddit
Email
origis energy
Origis Energy’s Mississippi portfolio will have a combined capacity of 550MW. Image: Origis Energy

US renewable energy developer Origis Energy has commissioned a 150MW solar-plus-storage project in the US state of Mississippi.

The project, Golden Triangle II, includes a 50MW battery energy storage system (BESS), and started producing electricity on 21 May. The project is part of a three-facility portfolio, including the Golden Triangle I project and the Optimist project, which each have 200MW of solar generation capacity alongside 50MW of BESS capacity. This is the largest storage portfolio under construction in Mississippi, and Origis expects to commission all three projects next year.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“Solar energy enhances Mississippi’s economic competitiveness, and Origis is removing limits to a cleaner, brighter future by building the region’s clean-energy infrastructure,” said Origis chief commercial and procurement officer Johan Vanhee. “Golden Triangle II is the first step in fostering a zero-carbon economy across the state that supports our nation’s economic and energy security goals.”

Origis signed a power purchase agreement (PPA) to sell power generated at the projects to the Tennessee Valley Authority (TVA), a utility, at what the companies called “competitive rates”. TVA will use the power to meet the energy demand of its large industrial customers, including Meta, which is among the leaders in clean power acquisition in the US, having signed a PPA with Pine Gate Renewables earlier this week.

TVA has announced plans to expand its renewable energy portfolio in recent years, aiming to add 10GW of new solar generation capacity by 2035, up from 2.4GW in operation currently. The TVA operates predominantly in Mississippi, which has one of the smaller solar sectors in the US, with the Solar Energy Industries Association (SEIA) expecting developers to add just 2.2GW of new capacity to the Mississippi solar sector in the next five years, 24th among the states.

In January, Origis announced that it had received US$317 million in funding from J.P. Morgan to support the development of both the Golden Triangle II project, and the 200MW Escalante Solar project in New Mexico.

Read Next

December 17, 2025
Doral Renewables has signed a PPA to sell power generated at its 270MW Lambs Draw solar PV project, which will be built in Kansas.
December 16, 2025
GameChange Solar will supply 1.2GW of trackers for ACWA Power’s 2GW Khulis solar PV project, currently under construction in Saudi Arabia.
December 12, 2025
A roundup of three solar PV project financing stories from Australia, Texas and California, with updates from Potentia Energy, Origis Energy and Baywa r.e.  
December 12, 2025
US solar PV module prices have stabilised at just over US$0.28/W in the three months to November 2025, according to Anza.
December 9, 2025
Equinor has started commercial operations at its first hybrid solar-plus-wind project in the Brazilian state of Bahia.
December 9, 2025
ACWA Power and Bapco Energies have signed an agreement to build a 2.8GW solar plant in Saudi Arabia, to be co-located with a BESS.

Upcoming Events

Upcoming Webinars
December 17, 2025
2pm GMT / 3pm CET
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 24, 2026
Dallas, Texas
Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA