Analyst: ‘Exhausted’ Indian solar industry would welcome transmission delay relief

March 11, 2020
Facebook
Twitter
LinkedIn
Reddit
Email
A transmission line in the South Indian state of Tamil Nadu. Credit: Tom Kenning

The Indian government has made recommendations to alleviate renewable energy project developers from having to bear the burden of costs incurred by delays in transmission infrastructure commissioning.

The Ministry of New and Renewable Energy (MNRE) last month issued an office memorandum aiming to address this “major issue” caused by time gaps between the commissioning of renewable energy projects and transmission systems.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

At present, the costs incurred during delay periods is borne by renewable energy generators even if there is no fault on their part, and MNRE said “the majority of solar and wind developers are suffering” as a result.

The Ministry recommended that in cases where renewable energy projects are delayed due to ‘Force Majeure’ reasons and the transmission system is installed on schedule, then the developer will bear the costs.

If such projects are delayed due to ‘Force Majeure’ and the transmission system is commissioned before the renewable energy projects, then the cost of transmission during the period of delay should be ‘socialised’, in other words, shared equally by the various off-takers such as utilities and distribution licensees.

If the transmission system is delayed due to Force Majeure and the renewables project is commissioned on time, then the costs should also be socialised.

However, if the transmission system is delayed for any reason other than Force Majeure, then the agency responsible for installing the transmission system will be held responsible.

MNRE has directed the Central Electricity Regulatory Commission (CERC) to include the suggestions of the memorandum in the final version of the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations.

Vinay Rustagi, managing director of consultancy firm Bridge to India, told PV Tech: “This would be a welcome relief for the industry, which is feeling exhausted by dealing with one challenge after another.”

Indeed, Indian developers have already seen their projects plunged into further delays due to the outbreak of the COVID-19 virus, although the government has already stepped in to extend commissioning deadlines as a result.

While utility-scale solar has started to boom in India over the last five years, analysts have persistently warned that transmission infrastructure rollout was not keeping up to the required pace. The forecasted bottleneck resulting from this is now visibly impacting the industry. India’s transmission system not only needs expansion to meet the increasing addition of renewable energy generation but also to meet huge rises in projected energy demand over the coming years.

India is projected to reach solar and wind power capacity of 82GW and 53GW respectively by the end of 2024 assuming a largely status-quo policy environment, according to a recent Bridge to India report.

Read Next

November 26, 2025
Indian solar PV manufacturer Vikram Solar has started commercial operations at its 5GW Vallam module manufacturing facility in India.
November 26, 2025
India has added 11GW of solar PV capacity during the third quarter of 2025, according to a report from the Institute for Energy Economics and Financial Analysis (IEEFA).
November 25, 2025
ACME Platinum has signed a PPA with the Solar Energy Corporation of India (SECI) for a 200MW solar-plus storage project in India.
November 24, 2025
India’s Railway Energy Management Company (REMC) has awarded 1GW of contracts to supply the railway network with round-the-clock (RTC) renewable energy.
November 21, 2025
ib vogt has entered a strategic partnership with Ingka Investments for a 210MW solar project in Rajasthan, India.
November 19, 2025
PVV Infra has outlined plans to build a 1GW TOPCon solar cell production line in the Indian state of Andhra Pradesh.

Upcoming Events

Solar Media Events
December 2, 2025
Málaga, Spain
Upcoming Webinars
December 4, 2025
2pm GMT / 3pm CET
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 24, 2026
Dallas, Texas
Solar Media Events
April 15, 2026
Milan, Italy