Analyst: ‘Exhausted’ Indian solar industry would welcome transmission delay relief

Facebook
Twitter
LinkedIn
Reddit
Email
A transmission line in the South Indian state of Tamil Nadu. Credit: Tom Kenning

The Indian government has made recommendations to alleviate renewable energy project developers from having to bear the burden of costs incurred by delays in transmission infrastructure commissioning.

The Ministry of New and Renewable Energy (MNRE) last month issued an office memorandum aiming to address this “major issue” caused by time gaps between the commissioning of renewable energy projects and transmission systems.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

At present, the costs incurred during delay periods is borne by renewable energy generators even if there is no fault on their part, and MNRE said “the majority of solar and wind developers are suffering” as a result.

The Ministry recommended that in cases where renewable energy projects are delayed due to ‘Force Majeure’ reasons and the transmission system is installed on schedule, then the developer will bear the costs.

If such projects are delayed due to ‘Force Majeure’ and the transmission system is commissioned before the renewable energy projects, then the cost of transmission during the period of delay should be ‘socialised’, in other words, shared equally by the various off-takers such as utilities and distribution licensees.

If the transmission system is delayed due to Force Majeure and the renewables project is commissioned on time, then the costs should also be socialised.

However, if the transmission system is delayed for any reason other than Force Majeure, then the agency responsible for installing the transmission system will be held responsible.

MNRE has directed the Central Electricity Regulatory Commission (CERC) to include the suggestions of the memorandum in the final version of the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations.

Vinay Rustagi, managing director of consultancy firm Bridge to India, told PV Tech: “This would be a welcome relief for the industry, which is feeling exhausted by dealing with one challenge after another.”

Indeed, Indian developers have already seen their projects plunged into further delays due to the outbreak of the COVID-19 virus, although the government has already stepped in to extend commissioning deadlines as a result.

While utility-scale solar has started to boom in India over the last five years, analysts have persistently warned that transmission infrastructure rollout was not keeping up to the required pace. The forecasted bottleneck resulting from this is now visibly impacting the industry. India’s transmission system not only needs expansion to meet the increasing addition of renewable energy generation but also to meet huge rises in projected energy demand over the coming years.

India is projected to reach solar and wind power capacity of 82GW and 53GW respectively by the end of 2024 assuming a largely status-quo policy environment, according to a recent Bridge to India report.

Read Next

October 6, 2025
Indian infrastructure company focused on rooftop and ground-based solar power installations, PVV Infra has secured solar power orders worth INR7.9 billion (US$90 million) through two of its subsidiaries. 
October 6, 2025
Indian solar developer ACME Group has established a new subsidiary to manage its renewable equipment manufacturing business, under which it is planning to scale production of TOPCon PV modules.
October 6, 2025
Rajasthan government will develop 500MW/2,000MWh of standalone battery energy storage systems (BESS) with a four-hour single-cycle configuration and extended operational life.
October 2, 2025
The Indian solar industry has 86GW and 182GW of solar cell and module manufacturing capacity, respectively, expected to be commissioned by 2027.
October 2, 2025
The Indian Department of Commerce has launched an antidumping investigation on solar encapsulants originating or exported from South Korea, Vietnam and Thailand.
September 29, 2025
Indian solar manufacturer Waaree has said it does not expect to pay additional duties on its solar cell imports to the US, following the start of an antidumping and countervailing duty (AD/CVD) investigation by the US Customs and Border Patrol (CBP).

Subscribe to Newsletter

Upcoming Events

Solar Media Events
October 7, 2025
Manila, Philippines
Solar Media Events
October 7, 2025
San Francisco Bay Area, USA
Solar Media Events
October 21, 2025
New York, USA
Solar Media Events
November 25, 2025
Warsaw, Poland