‘No plans’ to change India’s BCD amid module shortage, investment needing to double to hit climate targets

June 13, 2022
Facebook
Twitter
LinkedIn
Reddit
Email
RK Singh doubled down on India’s basic customs duty, claiming PV manufacturing of cells and modules had already risen in response. Image: MNRE

The Indian solar sector looks set for significant levels of disruptions over the next two years, with the government’s drive to establish a domestic manufacturing base risking deployment and investments needing to double if it is to meet its climate targets, according to industry analysts.

Last week, India’s Minister for Power, New and Renewable Energy, RK Singh, doubled down on support for the country’s basic custom duty (BCD) on solar cells (25%) and modules (40%), telling reporters there were “no plans” to change the system despite soaring module costs and a limited domestic supply.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“I don’t want any Chinese imports and want everything Made in India,” Singh is reported as saying, adding that India’s domestic manufacturing capacity of modules and cells had already started going up following the implementation of the BCD in April.

But analysts PV Tech spoke to following the comments were sceptical India’s nascent manufacturing sector would be able to fill demand fast enough. “The strategy to develop a domestic supply chain is understandable after the pandemic,” said Raj Prabhu, CEO and co-founder of analysts Mercom Capital. “[But] enforcing this policy hastily could create component shortages and price increases, which will slow installations.

“I would expect the government to take steps to ensure the market does not slow down and its short-term and long-term installation goals are met.”

Furthermore, Vinay Rustagi, managing director of research company Bridge to India (BOI) told PV Tech “the policy shift from capacity addition to Make in India is going to have a significant impact on deployment over the next 18-24 months.”

“Consumers are not willing to accept higher costs with customs duty of up to 40%,” said Rustagi. “Imports have already fallen sharply and domestic manufacturing capacity will be insufficient for another two years.”

Moreover, inflation is already causing significant disruption across India’s solar industry, with sustained rises in module prices, commodity price inflation and soaring freight rates causing massive upward pressure on Indian modules, with prices up 38% on mid-2020 levels. Many developers have resorted to stockpiling modules amid supply fears.  

A recent analysis by Crisil, a S&P Global company, revealed that those factors had also pulled down the return on equity (ROE) for 25GW of India solar projects, with 5GW of those at high risk.

Meanwhile, as India’s solar sector grapples with a range of disrupting factors, the Institute for Energy Economics and Financial Analysis (IEEFA) has said solar investments in the country will need to more than double if its to meet its climate targets.

It showed that while there was a record US$14.5 billion invested in India’s renewable energy sector in the last financial year, investment will have to more than double to US$30-US$40 billion annually for India to reach its target of 450GW of renewable energy capacity by 2030.

IEEFA energy economist and India lead, Vibhuti Garg, said the energy transition in India will require the government to act “as an enabler by rolling out ‘big bang’ policies and reforms to accelerate the deployment of renewable energy.”

“This means not only increasing investment in wind and solar power capacity, but also in creating an entire ecosystem around renewable energy,” she said.

25 November 2025
Warsaw, Poland
Large Scale Solar Central and Eastern Europe continues to be the place to leverage a network that has been made over more than 10 years, to build critical partnerships to develop solar projects throughout the region.

Read Next

October 27, 2025
Engie has signed additional PPAs with Meta, expanding their partnership to more than 1.3GW across four solar projects in Texas.
October 27, 2025
Waaree Energies has secured four solar module supply contracts totalling 692MW – three for projects in India and one in the US through its subsidiary.
October 27, 2025
Premier Energies has acquired a 51% stake each in transformer maker Transcon and inverter producer KSolare Energy. 
October 27, 2025
US solar technology company Swift Solar has deployed perovskite solar technology as part of a Department of Defence cyber warfare exercise in the state of Virginia.
October 27, 2025
Australian solar developer, BNRG Leeson, has submitted plans for a 440MW solar PV facility in Victoria's Campaspe Shire to Australia’s Environment Protection and Biodiversity Conservation (EPBC) Act.
October 24, 2025
The Emirati state-owned renewables developer Masdar has begun construction on a giant solar-plus-storage project in Abu Dhabi.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
November 25, 2025
Warsaw, Poland
Solar Media Events
December 2, 2025
Málaga, Spain
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 10, 2026
Frankfurt, Germany
Solar Media Events
March 24, 2026
Lisbon, Portugal