Building solar under quarantine: Ibox Energy on 50MW launch in Spain

Facebook
Twitter
LinkedIn
Reddit
Email
The €37m plant has been financed by Ibox Energy and Triodos and will sell power via a PPA with energy trader Nexus Energía. Image credit: Ibox Energy

Safety measures and PV-keen financiers have allowed a subsidy-free solar venture to break ground in the midst of Spain’s national quarantine, with plans for completion before year-end.

In recent days, partnership Ibox Energy announced that the deployment of a 50MW PV project in Southern Spain launched in the days after Monday 13 April, when Spain lifted a 10-day construction freeze enacted to limit the spread of COVID-19 across non-essential sectors.

This article requires Premium SubscriptionBasic (FREE) Subscription

Unlock unlimited access for 12 whole months of distinctive global analysis

Photovoltaics International is now included.

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Unlimited digital access to the PV Tech Power journal catalogue
  • Unlimited digital access to the Photovoltaics International journal catalogue
  • Access to more than 1,000 technical papers
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

Contacted by PV Tech, a spokesperson from Ibox Energy – a partnership between developers Ibexia Development and Cox Energy – spelled out the safety measures implemented at the 100GWh-a-year subsidy-free site in Posadas, to the west of the Andalusian city of Córdoba.

Construction will be handled by Beijing-headquartered EPC PowerChina Group and require 200 workers during its peak phase, the spokesperson said, adding that the numbers of onsite staff have been increased to offset the pause brought about by Spain’s construction freeze.

From sanitary masks to gloves, work shifts and social distancing, all of the legally required safety measures have been rolled out to minimise potential COVID-19 infections in line with authorities’ recommendations, the spokesperson added.

Solar components of the 50MW subsidy-free Posadas plant

Monocrystalline modules Inverters Structure
440W Number of inverters: 18+1 Solar tracker over Genius Tracker axis
144 half-cut cells Nominal power: 2550 kVA @40°C Pitch: 12 m
Maximum voltage of 1500V Maximum power: 2600 kVA @25°C Setup: 2Vx56, 2Vx42 and 2Vx28
Dimensions of 2094x1038x35mm Independent MPPTs: 12 Rotation range: ±55º
Source: Ibox Energy

No finance headwinds for €37m subsidy-free plant

Spain’s removal on 13 April 2020 of the 10-day stay-at-home obligation for construction workers paved the way for a restart of solar deployment. From utility Iberdrola to EPC Solarpack and oil major Repsol, industry players have confirmed solar work has resumed since that day.

Quizzed over any pandemic-driven hold-ups with shipments, the Ibox Energy spokesperson said the core components of the 50MW plant (see table above) have been delivered without issue, while certain “minor” equipment has seen slight delays.

“The reactivation of China’s economy is allowing us to maintain the already committed shipment deadlines,” said the spokesperson. They would not identify the PV suppliers Ibox Energy is working with, other than describing them as firms with a “proven track record” and “high production capacity”.

Some in Spain have warned the crash in power prices is putting financiers off solar but according to the spokesperson, the 50MW Posadas project has not faced difficulties on this front. Financing for the €37 million (US$40 million) plant has, they reported, followed the “usual procedures”.

The subsidy-free project will be financed with investment from Ibox Energy and Triodos Bank. Power from the 50MW plant will flow to PPA offtaker Nexus Energía, an energy trading firm. The transaction is the first solar PPA deal Triodos has financed in Spain, the spokesperson said.

Overall, Ibox Energy is eyeing a 1.5GW solar pipeline at various stages of development, set to go live across six Spanish regions within the next two years. Image credit: Ibox Energy

Plans for completion by Q4 2020 as 1.5GW pipeline looms

According to Ibox Energy, the plan is to take the subsidy-free 50MW plant to the finish line before the end of 2020. “We will fulfil our commitments,” the spokesperson said. “The plant will be operational by the year’s last quarter, [after] around six months.”

The Posadas solar plant is one of a series Ibox Energy is staging over the next few years. In the first half of 2020, the partnership is eyeing an 89MW solar project in Manzanares, in the Ciudad Real province, followed by further ventures.

All in all, Ibox Energy’s current solar pipeline exceeds 1.5GW across Spain. The assets, split across different development phases, are scheduled to go live within the next two years in Extremadura, Andalusia, Aragon, Catalonia, Castilla y León and Castilla-La Mancha.

Cox Energy in particular was the developer behind what was reported as one of the largest solar PPAs back in 2018. In March that year, the firm enlisted energy distributor Audax Renovables as the offtaker for a 660MW solar pipeline, equal to an annual supply of 1,300GWh.

PV Tech has set up a dedicated tracker to map out how the COVID-19 pandemic is disrupting solar supply chains worldwide. You can read the latest updates here.

If you have a COVID-19 statement to share or a story on how the pandemic is disrupting a solar business anywhere in the world, do get in touch at [email protected] or [email protected].

Read Next

Subscribe to Newsletter

Upcoming Events

Solar Media Events
May 1, 2024
Dallas, Texas
Solar Media Events
May 21, 2024
Sydney, Australia