SolarCity’s 1GW Buffalo fab tool install and ramp schedule hit by extended lead times

February 10, 2016
Facebook
Twitter
LinkedIn
Reddit
Email
Construction of the facility was started in September, 2014 with plant construction including internal facilities guided to be completed by the end of 2015.

SolarCity, the largest residential solar PV installer in the US said in its fourth quarter 2015 earnings call that its ambitious 1GW Buffalo Riverbend manufacturing facility had been impacted by longer than expected equipment lead times, pushing some equipment installs into the second-half of 2016. 

Construction of the facility was started in September, 2014 with plant construction including internal facilities guided to be completed by the end of 2015.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

However, internal facilities were still being installed in January and previous SolarCity management remarks on manufacturing equipment install schedules, meant initial tool installs would slip from the first quarter to the second quarter of 2016.

Lindon Rive, SolarCity's chief executive officer, noted in the latest earnings call that all building work should be completed by the end of the first quarter or probably early second quarter, followed by initial tool install taking place in the second and third quarter of 2016. 

Rive also explained that longer than expected equipment lead times than originally expected would have a greater impact on the overall production ramp schedules and delay the purchase of an unidentified amount of the equipment until some time in 2017.

“So the building should be completed at the end of this quarter probably early Q2,” noted Rive in the call. “We'll then start moving in equipment. As some of the equipment has longer lead time then we originally expected. And so that equipment is going to arriving around Q2, Q3 next year. Because of that it will actually – the effect of that we can delay the purchasing of some of the other equipment and so a lot of the CapEx or probably about half the CapEx are actually moving to 2017.”

Initially, US$400 million of capital expenditure was planned for manufacturing equipment, which is being managed by the Research Foundation for the State University of New York as part of the NY State funding of the whole project. 

The shift of an unspecified amount of capex into 2017, indicates that the initial plans to have the facility fully-ramped (annualized) in early 2017 would not be achieved.

Read Next

December 3, 2025
The Australian Renewable Energy Agency (ARENA) has announced up to AU$151 million (US$98 million) in conditional funding for Sunman Energy to establish a 500MW per annum solar module manufacturing facility in the Hunter Valley, New South Wales (NSW).
December 1, 2025
Multinational solar manufacturer Canadian Solar will assume direct control of its US solar PV and energy storage manufacturing operations, in a strategic move which may reduce its supply chain risks.
Premium
December 1, 2025
Steven Xuereb of Kiwa PI Berlin discusses the PV industry’s progress in addressing performance and reliability concerns around TOPCon technology.
November 28, 2025
The European Patent Office (EPO) has revoked a patent for a key solar cell manufacturing process, which has been hailed as “good news” for European solar PV manufacturing.
November 28, 2025
Chinese module manufacturer Huasun Energy has launched a new heterojunction module with a 760 W output, a 2,000 V system voltage and 24.5% module efficiency.
November 27, 2025
The Solar Stewardship Initiative (SSI) and the Copper Mark have signed an agreement to pursue “responsible production and sourcing of copper across the solar energy value chain”.

Upcoming Events

Upcoming Webinars
December 17, 2025
2pm GMT / 3pm CET
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 24, 2026
Dallas, Texas
Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA