SolarCity’s 1GW Buffalo fab tool install and ramp schedule hit by extended lead times

February 10, 2016
Facebook
Twitter
LinkedIn
Reddit
Email
Construction of the facility was started in September, 2014 with plant construction including internal facilities guided to be completed by the end of 2015.

SolarCity, the largest residential solar PV installer in the US said in its fourth quarter 2015 earnings call that its ambitious 1GW Buffalo Riverbend manufacturing facility had been impacted by longer than expected equipment lead times, pushing some equipment installs into the second-half of 2016. 

Construction of the facility was started in September, 2014 with plant construction including internal facilities guided to be completed by the end of 2015.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

However, internal facilities were still being installed in January and previous SolarCity management remarks on manufacturing equipment install schedules, meant initial tool installs would slip from the first quarter to the second quarter of 2016.

Lindon Rive, SolarCity's chief executive officer, noted in the latest earnings call that all building work should be completed by the end of the first quarter or probably early second quarter, followed by initial tool install taking place in the second and third quarter of 2016. 

Rive also explained that longer than expected equipment lead times than originally expected would have a greater impact on the overall production ramp schedules and delay the purchase of an unidentified amount of the equipment until some time in 2017.

“So the building should be completed at the end of this quarter probably early Q2,” noted Rive in the call. “We'll then start moving in equipment. As some of the equipment has longer lead time then we originally expected. And so that equipment is going to arriving around Q2, Q3 next year. Because of that it will actually – the effect of that we can delay the purchasing of some of the other equipment and so a lot of the CapEx or probably about half the CapEx are actually moving to 2017.”

Initially, US$400 million of capital expenditure was planned for manufacturing equipment, which is being managed by the Research Foundation for the State University of New York as part of the NY State funding of the whole project. 

The shift of an unspecified amount of capex into 2017, indicates that the initial plans to have the facility fully-ramped (annualized) in early 2017 would not be achieved.

16 June 2026
Napa, USA
PV Tech has been running PV ModuleTech Conferences since 2017. PV ModuleTech USA, on 16-17 June 2026, will be our fifth PV ModulelTech conference dedicated to the U.S. utility scale solar sector. The event will gather the key stakeholders from solar developers, solar asset owners and investors, PV manufacturing, policy-making and and all interested downstream channels and third-party entities. The goal is simple: to map out the PV module supply channels to the U.S. out to 2028 and beyond.
13 October 2026
San Francisco Bay Area, USA
PV Tech has been running an annual PV CellTech Conference since 2016. PV CellTech USA, on 13-14 October 2026 is our third PV CellTech conference dedicated to the U.S. manufacturing sector. The events in 2023, 2024 and 2025 were a sell out success and 2026 will once again gather the key stakeholders from PV manufacturing, equipment/materials, policy-making and strategy, capital equipment investment and all interested downstream channels and third-party entities. The goal is simple: to map out PV manufacturing in the U.S. out to 2030 and beyond.

Read Next

April 22, 2026
Chinese PV manufacturer Aiko has issued two major announcements regarding its plans to accelerate production of its high-efficiency all-back-contact (ABC) technology.
April 21, 2026
According to Ember's Global Electricity Review 2026, renewables accounted for 33.8% of global power generation in 2025.
April 21, 2026
Two US solar companies have made advances in perovskite-silicon solar module production this week, with claims that they mark a step towards making the long-discussed technology commercially viable.
Premium
April 21, 2026
PV Tech Premium spoke with the CEOs of Caelux and Solx about bringing US perovskite technology to the market at large.
April 20, 2026
Chinese PV manufacturer JinkoSolar has launched a new lightweight solar module designed for low-load-bearing rooftops.
April 20, 2026
US Customs and Border Protection (CBP) has detained solar modules produced by Vietnam-based solar manufacturer VSUN under the Uyghur Forced Labor Prevention Act (UFLPA).

Upcoming Events

Upcoming Webinars
May 27, 2026
9am BST / 10am CEST
Media Partners, Solar Media Events
June 3, 2026
National Exhibition and Convention Center (Shanghai)
Solar Media Events
June 16, 2026
Napa, USA
Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain