Indian state-owned power equipment manufacturer Bharat Heavy Electricals Limited (BHEL) has won an order to build three extra high voltage (EHV) substations in the state of Karnataka to transmit power from a major solar park.
The order for Power Grid Corporation of India (Powergrid) is valued at INR960 million (US$14 million) having been won in an ADB-funded international competitive tender.
Try Premium for just $1
- Full premium access for the first month at only $1
- Converts to an annual rate after 30 days unless cancelled
- Cancel anytime during the trial period
Premium Benefits
- Expert industry analysis and interviews
- Digital access to PV Tech Power journal
- Exclusive event discounts
Or get the full Premium subscription right away
Or continue reading this article for free
This will include substations of 400/220kV at Pavagada and Vasantnarsapur in Tumkur as well as a 400kV substation at Mysore.
The 400/220kV substations will transmit power from what BHEL claims will be India's largest solar park, set for 2GW at the Pavagada district, on 4,046 hectares of land. The substations are expected to be commissioned within 18 months.
Equipment will be supplied by BHEL's manufacturing Units at Bhopal and Bangalore.
BHEL is already carrying out 765kV substation orders for Powergrid in Gujarat and Rajasthan under the Green Energy Corridor scheme.
Mercom Capital Group recently said that India’s long-term renewable energy future requires adding transmission capacity and removing bottlenecks immediately, while some developers have faced project delays as a direct result of behind schedule transmission infrastructure.
SECI 2MW port solar tender
In more India news, Solar Energy Corporation of India (SECI), on behalf of Kolkata Port Trust, has invited bids for the development of a 2MW(ac) solar PV project at Haldia Dock Complex Premises, Haldia, West Bengal.