India mulls solar project deadline extensions to help with coronavirus delays

Facebook
Twitter
LinkedIn
Reddit
Email
Source: CC0 Public Domain

India is considering extending solar commissioning deadlines in order to counter the disruption caused by the coronavirus on Chinese solar imports, the renewable energy secretary said on Tuesday.

The news, reported in the Economic Times on Wednesday, follows a Crisil report that warned that 3GW of solar projects worth INR 16,000 crore (US$2.238 billion) were at risk of incurring penalties for missing their scheduled commercial operation date (SCOD).

Anand Kumar, new and renewable energy secretary, told news outlets that the government would consider loosening schedules if developers can prove shipment delays due to the virus.

India sources 80% of its solar modules from China, where supply chains, manufacturing processes and transportation have been ruptured as the country deals with the deadly virus.

A raft of the world’s largest solar manufacturing players – including Jinko Solar, JA Solar, SolarEdge, Canadian Solar, LONGi Group, Trina Solar, Q-CELLS and JA Solar – operate in provinces where extended work stoppages were in place, according to a report published in late January by ROTH Capital Markets that forecast a near-term rise in component pricing.

Orders for modules are typically placed with a lead time of six months from commissioning, according to Manish Gupta, senior director at Crisil, meaning that “around 3GW” of solar projects auctioned between July and August 2018 with July 2020 SCODs are at risk of costly delays.

For a 100MW solar project, the typical penalty for missing its SCOD jumps from: INR 20 crore (US$2.8 million) for the first 30 days (pro rata on a per day basis), to INR 80 crore (US$11.2 million) for the next 60 (pro rata on a per day basis), to a tariff revision after three months.

Bridge to India: Extension would provide "only partial relief"

Vinay Rustagi, director of renewables consultancy Bridge to India, told PV Tech that the firm estimates that “about 2GW” of solar projects are set to be affected if solar shipments from China resume “within two to three months.”

“The number would be much larger if the disruption drags out,” he said, noting that there is a pipeline of more than 10GW of projects in India due for completion this year.

Rustagi added that an extension of completion deadlines will only go so far in dealing with the problem.

“We are confident that the government would be sympathetic and extend completion timelines as necessary,” he said. “But that is only partial relief. The developers would still tend to lose substantially because of higher working capital and financing costs, extra transmission charges, etc…”

Developers can also opt to invoke a ‘force majeure’ clause written into all government power purchase agreements (PPA), which allows them to seek relief under unforeseen and uncontrollable events, or opt to purchase more expensive modules sourced outside of China to meet their deadlines.

Both alternatives are far from ideal for developers: The clause is yet to be tested and could face legal and regulatory hurdles, whereas non-Chinese components are typically 15-20% more expensive, according to Crisil.

The coronavirus, which broke out in late December, has now killed more than 2,000 people to date and infected some 72,000, according to the World Health Organisation.

BloombergNEF: Virus’ impact on solar “isn’t going to be massive” if contained by June

The impact of the coronavirus on solar supply chains has been felt beyond India.

South Korea’s Hanwha Solutions has temporarily shut down two major module assembly plants due to Chinese component shortages. Taiwan market research firm TrendForce has noted that the country is set to miss its targeted installation capacity for 2020 for the same reason.

BloombergNEF solar analyst Jenny Chase said that long-term production will weather the outbreak.

“On solar, the effect [of the coronavirus] probably isn't going to be massive, provided the outbreak is contained in Q2,” she wrote on Twitter on Wednesday.

“There is plenty of capacity once logistics and worker availability is back to normal, most demand can be delayed, but it's definitely unpleasant for the firms and people involved.”

Read Next

August 11, 2022
The financial adversity of India’s struggling distribution companies (Discoms) has been reflected in a significant downgrading in the latest rankings by the Ministry of Power, giving yet more concern for renewable energy players
August 10, 2022
Canadian Solar plans to build an integrated PV manufacturing plant in Western China, with a capacity of 200,000MT of high-purity polysilicon, 10GW of both cells and modules and multi-GW productions of raw and auxiliary materials.
August 8, 2022
The Inflation Reduction Act (IRA), which includes US$369 billion in energy security and climate change programmes over the next ten years, passed in the US Senate on Sunday, paving the way for its movement to the House of Representatives and subsequent signing by President Joe Biden.
August 8, 2022
India deployed 8,359MW of solar PV in the first half of the year, marking a significant increase of 71% compared to the same period last year
PV Tech Premium
August 8, 2022
The price of polysilicon in China rose across the board last week, despite signals that it may have stabilised, constituting the 25th round of price increases this year alone.
August 3, 2022
Tata Power subsidiary Tata Power Green Energy has commissioned a 225MW hybrid wind and solar project in the Indian solar hotbed state of Rajasthan.

Subscribe to Newsletter

Upcoming Events

Upcoming Webinars
September 7, 2022
15:30 AEST (UTC +10)
Solar Media Events
September 14, 2022
London
Solar Media Events
October 4, 2022
New York, USA
Solar Media Events
October 11, 2022
Virtual event