Adani commissions 50MW solar plant in India’s Uttar Pradesh

June 13, 2017
Facebook
Twitter
LinkedIn
Reddit
Email
Adani won the project with a bid of INR 4.78/kWh (US$0.07). Credit: Adani

Indian infrastructure conglomerate Adani Group has commissioned a 50MW solar PV plant at Mahoba district in the Indian state of Uttar Pradesh.

The plant, costing INR3.15 billion (US$48.9 million), used string inverter technology for the first time in Uttar Pradesh. The 132kV transmission line is 21.5 kilometres long and connected to the UPTCL Mahiba substation under an agreement signed with India’s largest utility NTPC. Adani won the project under the National Solar Mission programme, with a bid of INR 4.78/kWh (US$0.07) in January 2016.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Around 250 direct and indirect jobs were created during the development of the plant.

Jayant parimal, chief executive, renewable energy business, Adani Group, said: “We are delighted to have achieved the setting up of this plant, helping us prove our dedicated efforts towards nation building as well as showing our commitment to the government’s green energy mission. We are moving closer to our aim of revolutionising the renewable energy sector in India. We would like to extend our heartiest gratitude to the UP government officials for their support.”

The UP officials support complements energy minister Piyush Goyal’s recent announcement that he would get the UP city of Varanasi to challenge Munich to a race to become the world’s first city run on 100% clean energy. Goyal said the chief minister of UP was particularly supportive of sustainability policies.

Adani now has 838MW of operational PV capacity across Gujarat, Tamil Nadu (The second largest project in the world), Uttar Pradesh and Punjab. By the end of this year, Adani expects to have more than 2GW capacity installed.

Adani Green Energy as of recently is no longer a subsidiary of Adani Group after the group’s equity stake in the renewable energy was diluted below 50%.

Adani also recently approved plans to go ahead with its giant Carmichael coal mine in Australia, despite India’s intentions to maximise self-sufficiency in terms of coal consumption.

Read Next

April 10, 2026
India has become the third-largest country by installed renewable energy capacity, reaching 274.68, with over 150GW of solar PV capacity, according to statistics from the Ministry of New and Renewable Energy (MNRE).
Premium
April 10, 2026
Despite PV’s maturity, a new paper argues that its growing global significance makes ongoing research essential.
April 8, 2026
PV manufacturing capital expenditure is expected to rebound this year, following two years in the doldrums as the industry weathered a global oversupply of modules, new figures show.
Premium
April 8, 2026
After a sharp decline in 2023, PV manufacturing capital expenditure is set to bounce back this year, and not just in China, writes Moustafa Ramadan.
April 7, 2026
Sangam Solar One, a subsidiary of Indian solar PV manufacturer Waaree Energies, has commissioned a 3GW PV module manufacturing facility in Samakhiali, Kutch, Gujarat.
April 7, 2026
According to Ember, solar-plus-storage could supply up to 90% of India’s electricity demand at a levelised cost of electricity (LCOE) of INR5.06/kWh (US$56/MWh).

Upcoming Events

Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA
Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain
Solar Media Events
November 24, 2026
Warsaw, Poland