Maoneng, Decmil break ground on 255MW New South Wales solar project

February 26, 2019
Facebook
Twitter
LinkedIn
Reddit
Email
Maoneng is also now preparing another 500MW of solar to be commissioned in line with the proposed SA/NSW interconnector, together with additional energy storage. Credit: Maoneng Australia

EPC contractor Decmil has broken ground on the 255MW Sunraysia solar plant in Balranald, New South Wales, Australia, which is being developed by Maoneng Australia.

Construction on the plant will require 350-400 workers, with the installation of more than 755,000 JinkoSolar PV panels mounted onto single-axis trackers from NEXTracker, more than 4,000km of cables and 100,000 piles over 800 Hectares. A large-scale grid-connected energy storage project, named Sunraysia Emporium, will be located adjacent to the Sunraysia Solar Farm.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The PV project is expected to generate approximately 529GWh of energy per year when commissioned; which is the equivalent to powering up to 50,000 households.

The solar farm is connected to a 33/220kV substation co-located on-site where the energy is transferred to the Transgrid 220kV Balranald Substation. From there the energy is then transferred either towards Buronga/VIC or Darlington Point/NSW. As part of the works, approximately 400km of new fibre optic cable will be installed between the Buronga and Darlington Point substations to improve communication and control of the solar farm.

The project is supported by two Power Purchase Agreements (PPAs) under which UNSW Sydney and AGL Energy (AGL) will purchase energy over 15 years. It reached financial close with John Laing in October last year.

“As a responsible renewable energy developer, we are cognisant of the impact which renewable energy has, both good and bad. To improve the reliability and to minimise both the technical and commercial impact of our developments moving forward, we aim to implement energy storage systems capable of time-shifting large amounts of energy throughout the day. Only by doing this, as a matter of best practice, will we be able to transition towards a 100% renewable energy future,” said Qiao Nan Han, VP of Maoneng Group.

“Sunraysia is strategically placed to service multiple states and territories given its proximity to the proposed interconnectors and the main charging route for the Snowy 2.0. AEMO’s ISP (Integrated System Plan) looks at various scenarios including the development of a large Renewable Energy Zone here at Balranald. We are excited to be part of this moving feast and welcome the challenges and responsibilities which come with these developments,” Nan Han added.

Maoneng is also now preparing another 500MW of solar to be commissioned in line with the proposed SA/NSW interconnector, together with additional energy storage.

Australia is a global frontrunner in large-scale solar-plus-storage projects, with regular project announcements over the last year.

Read Next

Sponsored
October 23, 2025
Tongwei's rooftop-focused TNC 2.0 G12R-48 module will be among the products on show at All Energy Australia next week.
October 23, 2025
Spanish power electronics specialist Ingeteam has won a contract to supply inverters and control systems for European Energy Australia's 100MW Winton North solar-plus-storage project in northeast Victoria.
October 23, 2025
Queensland's rooftop solar systems have exceeded 5GW of output for the first time, marking a milestone in Australia's solar expansion.
October 22, 2025
The Queensland government has launched the Social Licence in Renewable Energy Toolkit, providing local councils in Australia with resources to navigate renewable energy project engagement and community consultation processes.
October 21, 2025
Australia's solar-plus-storage sector gained momentum with 725MW of solar PV approvals advancing across New South Wales and Queensland.
October 21, 2025
Luminous Robotics has successfully completed its first international deployment of AI-powered solar installation robots at Engie’s 250MW Goorambat East Solar Farm in Victoria, Australia.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
November 25, 2025
Warsaw, Poland
Solar Media Events
December 2, 2025
Málaga, Spain
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 10, 2026
Frankfurt, Germany