Mytilineos’ renewables unit takes financial hit from project delays in 2020

Facebook
Twitter
LinkedIn
Reddit
Email
Mytilineos was the engineering, procurement and construction contractor for the 170MW Atacama Solar project (pictured) in Chile. Image: Mytilineos.

Greek industrial group Mytilineos said 2020 turnover from its renewables and storage development unit was around 40% lower than forecasted due to contracting and construction delays as a result of the coronavirus pandemic.

The unit’s turnover was down 32% year-on-year to €264 million (US$316 million), while earnings before interest, taxes, depreciation and amortisation (EBITDA) almost halved (down 48%) to €15 million.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Despite the challenging circumstances, the company completed engineering, procurement and construction contracts last year for the 170MW Atacama PV plant in Chile and the 300MW Talasol park in Spain.

In terms of build-operate-transfer projects in the renewables business, Mytilineos said its portfolio has reached 4.3GW of capacity, including facilities in countries such as Greece, Spain, the UK, Chile, Mexico, South Korea, Taiwan and Australia.

While the impacts of the pandemic were strongly felt in the renewables unit in the first nine months of the year, a “gradual recovery” was noted in the last quarter, with the signing of new projects and the normalisation of construction progress.

With the unit undertaking new projects and investments in targeted markets, Mytilineos said the renewables development business will be a “significant catalyst” for the firm’s operational profitability in the coming year.

For the company as a whole, 2020 turnover was €1.9 billion, down 16% year-on-year, while EBITDA increased 1% to €315 million.

Mytilineos said the improvement of Greek electricity consumption and gradual increase of power prices as well as the progress of new renewables projects are setting a “solid foundation for a strong financial performance in 2021”.

Read Next

November 13, 2026
Greek developer Metlen Energy and Metals and Greek maritime company Tsakos Group have started construction at a 251.9MW solar-plus-storage project in Greece.
November 6, 2026
US tracker manufacturer FTC Solar has registered revenues of US$32.8 million in the third quarter of 2026, up both sequentially (25.4%) and year-on-year (26.1%).
November 5, 2026
Sunrun reports 5GWh of networked storage capacity in the third quarter of 2026, while solar additions reached 204MW.
November 2, 2026
Chinese leading solar PV manufacturer Jinko has shipped 15GW of solar modules in the third quarter of 2026.
October 30, 2026
Norwegian independent power producer (IPP) Scatec has been impacted by an impairment loss from its solar PV plants and intangible assets in Ukraine and Pakistan during its third quarter results for 2026.
October 29, 2026
Nextpower has reported net income of US$165 million and revenue of over US$1.1 billion in its results for the quarter ending 2 October.

Upcoming Events

Solar Media Events
November 24, 2026
Warsaw, Poland
Solar Media Events
February 2, 2027
London, UK
Solar Media Events
April 20, 2027
Istanbul, Türkiye