Queensland 25MW community solar online, Western Australia co-located PV farm nears construction

December 14, 2016
Facebook
Twitter
LinkedIn
Reddit
Email
The project received AU$22.8 million (US$17.1 million) funding from the Australian Renewable Energy Agency (ARENA). Credit: ARENA

The 25MW Barcaldine Remote Community Solar Farm in Queensland, Australia, has started feeding electricity to the grid two months ahead of schedule.

The plant developed by Elecnor Australia, a subsidiary of Spain-based energy firm Elecnor, is expected to reach full generation by the end of this year. It will be able power the equivalent of around 9,800 households by generating around 57,000MWh of clean energy per year. It includes more than 78,000 solar panels on single-axis trackers.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The project received AU$22.8 million (US$17.1 million) funding from the Australian Renewable Energy Agency (ARENA) and AU$20 million in debt finance from the Clean Energy Finance Corporation (CEFC).

ARENA chief executive Ivor Frischknecht said: “As well as generating clean energy, the project is demonstrating how project developers can monetise network benefits and ultimately how solar farms can improve network efficiency and reliability at the edge of the grid.”

Western Australia’s first co-located wind and PV farm

Energy infrastructure company APA Group will begin construction of the Emu Downs Solar Farm in Western Australia (WA) within two weeks following the signing of a funding agreement with ARENA. This is the first solar farm in WA to be co-located with wind turbines, in this case with APA’s existing 80MW Emu Downs Wind Farm.

Frischknecht said: “This approach saves money on grid connection, approvals and site development and reduces environmental impacts. Solar and wind are complementary renewable energy sources. As solar generates energy during the day, wind farms tend to generate more power overnight. In WA, co-locating wind and solar delivers more continuous energy generation and makes good business sense.

“Across the board, the move to co-location of wind and solar means solar plants can be rolled out more quickly and cheaply across the country. A recent ARENA-supported study found there’s an estimated 1000MW of potential opportunities to add solar alongside existing wind farms – that’s enough to power 700,000 homes.”

The plant will produce enough energy to power 6,700 homes while creating an estimated 100 jobs during construction, mostly in the local region.

Emu Downs Solar Farm has entered into a 12-year power purchase agreement (PPA) to sell electricity and generation certificates to energy retailer, Synergy.”

Major power firm EnergyAustralia recently confirmed it will soon sign PPAs for 500MW of wind and solar projects across eastern Australia, in contracts worth AU$1.5 billion (US$1.12 billion).

Read Next

November 14, 2025
NSW has removed regulatory barriers that previously prevented owners of heritage-listed properties from installing rooftop solar.
November 13, 2025
QIC and EDP Renewables Australia have signed an agreement to develop a 400MWac solar-plus-storage project in Toowoomba, Queensland.
November 13, 2025
Building a solar manufacturing supply chain has become a "strategic imperative" for Australia, Stellar PV CEO Louise Hurll told PV Tech.
Premium
November 13, 2025
PV Talk: Stellar PV has been awarded government funding for its plan to open a solar ingot and wafer plant in Australia. The company’s CEO Louise Hurll tells Shreeyashi Ojha why the time is right for Australia to develop its upstream manufacturing capacity.
Premium
November 12, 2025
Solar PV in Australia’s National Electricity Market (NEM) made a strong showing across October 2025, reaching 4,715GWh – a 9.88% increase on the 4,291GWh recorded in October 2024.
November 11, 2025
Developer Pacific Energy has signed a 20-year power purchase agreement (PPA) with Horizon Power to deliver a hybrid power system to the town of Leonora in Western Australia's goldfields, aiming for up to 60% renewable energy penetration by 2027.

Upcoming Events

Solar Media Events
November 25, 2025
Warsaw, Poland
Solar Media Events
December 2, 2025
Málaga, Spain
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 24, 2026
Lisbon, Portugal
Solar Media Events
June 16, 2026
Napa, USA