Walmart pins store fires on Tesla solar installs in new lawsuit

Facebook
Twitter
LinkedIn
Reddit
Email
In 2007, Wal-Mart launched a solar power pilot project to determine solar viability for their store portfolio. The pilot program consisted of 22 sites across California and Hawaii. Image: Blue Oak Energy

Walmart has linked a string of store fires in recent years to Tesla’s alleged mismanagement of solar panel installation and maintenance, taking Elon Musk’s outfit to court.

A new lawsuit from the US retail colossus demands damages from Tesla and the full removal of its solar installs, amid claims that the company's “systemic, widespread failures” were the culprit of a series of rooftop blazes over the past decade.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“To state the obvious, properly designed, installed, inspected, and maintained solar systems do not spontaneously combust, and the occurrence of multiple fires involving Tesla's solar systems is but one unmistakable sign of negligence by Tesla,” reads Walmart’s lawsuit.

The document – filed on Tuesday before the New York County Supreme Court – urges the tribunal to declare Tesla in breach of 240-plus contracts the firm entered with Walmart between 2010 and 2016, tasking it with the roll-out, running and maintenance of solar panels in hundreds of locations.

Hotspots ‘visible to the naked eye’

Walmart’s lawsuit sketches out a timeline for at least seven store blazes between 2012 and 2018, all of which the US retailer attributes to what it describes as Tesla’s “gross negligence”.

The series begins with three fires at Tesla-equipped stores: California’s Long Beach (2012) and Milpitas (2016) and Colorado’s Lakeside (2017). According to Walmart's estimates, the first two incidents cost around US$90,000 and US$500,000 in respective damages. 

The lawsuit's timeline continues with another three blazes throughout H1 2018 at locations fitted with Tesla installs. After the last of the three, another California blaze in May 2018, Walmart asked Tesla to disconnect all rooftop solar systems.

Tesla acquiesced but this, Walmart claimed, did not prevent a further blaze at California’s Yuba City facility with switched-off PV installs in November 2018. Investigations revealed wires were “still sparking” when the fire was discovered, the US retailer claimed.

According to the lawsuit, post-fire panel probing at various locations found “hotspots” – or “micro-crack” precursors – where heat and pressure were building. Tesla, the document alleges, routinely used staff lacking “basic solar training and knowledge” and the correct equipment to carry out inspections.

In the case of Yuba City’s fire, the document goes on to claim, a Tesla technician helped create a “fire hazard” by failing to shut a combiner box. Tesla staff, Walmart alleges, also failed to disclose a ground fault alert triggered at the location last summer.

Eyes on Musk amid solar relaunch

Whether and how Tesla responds to the lawsuit remains unclear at the time of writing. Contacted today by PV Tech, the firm had not offered any comment by the time this article was published.

The lawsuit claims Tesla has yet to offer a “complete set of final root cause analyses” of the key factors behind the string of fires. The Silicon Valley firm has not paid “one cent” of the out-of-pocket damages and other fees Walmart faced over four of the seven fires, the document alleges.

The lawsuit does not identify the solar module brands found in the stores in question. Figures from ROTH Capital show leading suppliers to its Californian PV installations in 2016 were REC Group (35% of all module supply), Kyocera (30%), Tesla itself (11%) and Trina Solar (8%).

Walmart claims to have made one last attempt for Tesla to respond to the accusations in July 2019, giving the firm a 30-day window to shed light on blaze causes and compensate Walmart over losses until that point. Tesla, Walmart alleges, failed to deliver on these points by 15 August, paving the way for the current lawsuit.

For Tesla, the prospect of litigation and controversy comes within days of a reboot of its solar panel business, featuring a new US rental service. “With the new lower Tesla pricing, it’s like having a money printer on your roof if you live a state with high electricity costs,” was how CEO Musk pitched the relaunch on Twitter over the weekend.

The firm has witnessed muted solar roll-out levels in recent quarters, hitting record-low deployment figures in Q2 2019 even as energy storage reached new highs. The Silicon Valley player, which acquired SolarCity in 2016, lost in recent times its spot as the US top residential installer to Sunrun.

See here to read the lawsuit and other case documents in full

US solar prospects will take centre stage at Solar Media's Solar & Storage Finance USA, to be held in New York on 29-30 October 2019

21 October 2025
New York, USA
Returning for its 12th edition, Solar and Storage Finance USA Summit remains the annual event where decision-makers at the forefront of solar and storage projects across the United States and capital converge. Featuring the most active solar and storage transactors, join us for a packed two-days of deal-making, learning and networking.
16 June 2026
Napa, USA
PV Tech has been running PV ModuleTech Conferences since 2017. PV ModuleTech USA, on 16-17 June 2026, will be our fifth PV ModulelTech conference dedicated to the U.S. utility scale solar sector. The event will gather the key stakeholders from solar developers, solar asset owners and investors, PV manufacturing, policy-making and and all interested downstream channels and third-party entities. The goal is simple: to map out the PV module supply channels to the U.S. out to 2027 and beyond.

Read Next

October 8, 2025
US solar module prices jumped in Q3 2025 as developers scrambled to meet the 2 September 2025 safe harbour deadline for Investment Tax Credit (ITC) qualification, according to supply chain platform Anza.
October 8, 2025
Despite policy headwinds on the federal level, there is optimism for the future of the US solar and storage sector.
October 7, 2025
Solar PV will account for almost 80% of the 4.6TW of new renewable power expected to be added by 2030, according to the International Energy Agency (IEA).
October 7, 2025
Doral Renewables has secured a PPA with an unnamed 'corporate buyer' for its 430MW Cold Creek solar-plus-storage project in Texas.
October 7, 2025
US independent power producer (IPP) Arevon has begun operations at two utility-scale solar projects in Indiana.
Premium
October 6, 2025
Talon PV aims to be the first US company to safely manufacture TOPCon cells at scale, backed by European technology and a crucial First Solar licensing deal.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
October 21, 2025
New York, USA
Solar Media Events
November 25, 2025
Warsaw, Poland
Solar Media Events
December 2, 2025
Málaga, Spain
Solar Media Events
February 3, 2026
London, UK