GCL-Poly’s FBR polysilicon production capacity on target for end of 2020

December 14, 2020
Facebook
Twitter
LinkedIn
Reddit
Email
GCL-Poly has set goals of reaching 30,000MT of FBR produced polysilicon by June 2021 and 54,000MT by the end of next-year. Image: GCL-Poly

Major polysilicon producer GCL-Poly Energy Holdings expects to meet previously set targets of achieving 10,000MT production capacity of its Fluidized Bed Reactor granular polysilicon technology by the end of 2020.

The 10,000MT target was noted in first-half year financial results, which included production of around 2,500MT in the reporting period with the goal of achieving 6,000MT at the end of June, 2020.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

GCL-Poly has set goals of reaching 30,000MT of FBR produced polysilicon by June 2021 and 54,000MT by the end of next-year at its manufacturing base in Xuzhou, Jiangsu province, via its subsidiary, Jiangsu Zhongneng Polysilicon.

It has taken almost five years for GCL-Poly to master the second generation FBR processes having acquired the technology from bankrupt SunEdison in 2016. The current production ramp has been very conservative to date, compared with major capacity ramps of the conventional Siemens polysilicon process by other producers in China. 

Read Next

December 2, 2025
Astronergy and JA Solar have 'reached an agreement on cross-licencing' of tunnel oxide passivated contact (TOPCon) patents moving forward.
December 1, 2025
Multinational solar manufacturer Canadian Solar will assume direct control of its US solar PV and energy storage manufacturing operations, in a strategic move which may reduce its supply chain risks.
Premium
December 1, 2025
Steven Xuereb of Kiwa PI Berlin discusses the PV industry’s progress in addressing performance and reliability concerns around TOPCon technology.
November 28, 2025
LONGi has acquired system integrator PotisEdge, and plans to launch an ‘Energy Storage One-Stop Solution’.
November 28, 2025
Chinese module manufacturer Huasun Energy has launched a new heterojunction module with a 760 W output, a 2,000 V system voltage and 24.5% module efficiency.
November 26, 2025
Module shipment and pricing patterns in Europe bear resemblance to last year’s oversupply, which resulted in substantial losses for many industry players, writes Filip Kierzkowski

Upcoming Events

Solar Media Events
December 2, 2025
Málaga, Spain
Upcoming Webinars
December 4, 2025
2pm GMT / 3pm CET
Upcoming Webinars
December 17, 2025
2pm GMT / 3pm CET
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 24, 2026
Dallas, Texas