Nevada’s NV Energy in major solar-plus-storage push

June 25, 2019
Facebook
Twitter
LinkedIn
Reddit
Email
At 3.452GW, Nevada was the US fourth largest PV market in installed capacity terms last year, according to industry figures (Credit: Flickr / Mobius in Mobili)

NV Energy has unveiled ambitions for a solar-plus-storage boom over five years, cementing its position among the US players tapping into the increasingly cost-efficient hybrid.

The Nevada utility said this week it will deploy close to 1.2GW of new PV and 590MW of battery energy storage, with plans to complete three projects near Las Vegas by 2023.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

At 690MW of PV capacity, the Gemini scheme is the biggest of the trio in Nevada’s Clark County and could, once delivered, become the state’s largest solar plant to date.

Designed with 380MW AC in additional battery storage capacity, Gemini will be co-developed by Quinbrook Infrastructure Partners and Arevia Power.

For its part, US IPP 8minute Solar Energy will be tasked with the roll-out of the Southern Bighorn Solar & Storage Center, featuring 300MW of PV and 135MW of four-hour li-ion battery units.

At Clark County, Gemini and Southern Bighorn will be joined by Arrow Canyon, an EDF development of 200MW of PV capacity and a further 75MW of five-hour battery storage systems.

Solar-plus-storage steals the spotlight

NV Energy’s plans mark the latest endorsement for solar-plus-storage, a hybrid fast approaching cost-competitiveness levels rivalling those of fossil fuel installations.

Warren Buffett’s Berkshire Hathaway Energy – NV Energy’s owner since 2013 – is among the utilities mulling moves from coal to solar-plus-storage, a decision experts argue could save millions.

NV Energy’s embrace of the hybrid is not new, however. Last year, the utility put forward a 1GW-plus PV pipeline across six projects, designed with an aggregate 100MW in battery storage.

The largest of the three, 300MW Eagle Shadow Mountain, is too being developed by 8minute at Nevada’s Clark County. Last May, it was said to be scheduled for completion by 2021.

In Nevada, deployment of solar PV and other renewables is being fostered under the so-called Senate Bill 358, which mandates a 50% renewable share across power providers by 2030.

At 3.452GW, the Silver State was the US fourth largest PV market in installed capacity terms last year, according to figures from solar body SEIA and Wood Mackenzie.

Read on for more information on NV Energy's Gemini scheme and Nevada's Senate Bill 358

16 June 2026
Napa, USA
PV Tech has been running PV ModuleTech Conferences since 2017. PV ModuleTech USA, on 16-17 June 2026, will be our fifth PV ModulelTech conference dedicated to the U.S. utility scale solar sector. The event will gather the key stakeholders from solar developers, solar asset owners and investors, PV manufacturing, policy-making and and all interested downstream channels and third-party entities. The goal is simple: to map out the PV module supply channels to the U.S. out to 2028 and beyond.

Read Next

Premium
January 9, 2026
PV Tech Premium spoke with Crux on the trends to look forward in 2026 in the clean energy transferable tax credit market.
January 9, 2026
The US has withdrawn from a number of UN climate organisations, including the Framework Convention on Climate Change, International Renewable Energy Agency (IRENA) and Intergovernmental Panel on Climate Change.
January 9, 2026
The Governor of Illinois, JB Pritzker, has signed a clean energy bill into law that will boost solar PV and energy storage investments in the state, among others.
January 8, 2026
ENGIE and Ampion added new solar capacity, Reactivate plans to build on landfill sites and Pivot has completed the first phase of a portfolio.
January 8, 2026
US renewables developer Adapture Renewables has secured US$233 million in tax equity from US Bank to support its 441MW Titanium solar PV project portfolio.
January 8, 2026
Solar manufacturing major Canadian Solar is looking to raise US$200 million in convertible senior note sales to support its US manufacturing operations

Upcoming Events

Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 24, 2026
Dallas, Texas
Solar Media Events
April 15, 2026
Milan, Italy
Solar Media Events
June 16, 2026
Napa, USA
Solar Media Events
November 24, 2026
Warsaw, Poland