‘Very disappointing’ under subscription for Gujarat’s 700MW solar tender

May 2, 2019
Facebook
Twitter
LinkedIn
Reddit
Email
GUVNL has cancelled two auctions in the past leading to some uncertainty for developers. Flickr: Arian Zwegers

Gujarat's 700MW solar PV tender has been undersubscribed by 100MW, in what one analyst has described as the latest poor show of interest in a worrying trend.

Companies submitting to Gujarat Urja Vikas Nigam Limited's (GUVNL) tender for capacity under Phase III of the Raghanesda Solar Park included:

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

  • Tata – 200MW
  • Engie – 200MW
  • GIPCL – 100MW
  • GSECL – 100MW

Vinay Rustagi, managing director of consultancy firm Bridge to India, told PV Tech: “It's very disappointing to see a series of under subscriptions and cancellations, which seem to be becoming norm. This trend betrays a lack of connect between the government and private sector and if not addressed urgently, will cause untold damage to investor confidence.”

GUVNL has cancelled two auctions in the past leading to some uncertainty for developers. It has also had to extend tenders for its 1GW Dholera Solar Park due to a lack of interest.

In February, GUVNL auctioned 500MW of grid-connected solar capacity with winning tariffs in the range of INR2.55-2.66/kWh (US$3.6-3.8 cents).

India has multi-gigawatts of solar out for tender, having been on a procurement binge since late December 2018, including its first large-scale solar-plus-storage issuances for two years. However, more undersubscribed offers will be met with great worry by a government that is throwing all its weight behind reaching its 100GW by 2022 solar target. 

Read Next

April 24, 2026
Indian module manufacturer Saatvik Green Energy has acquired an 80% equity stake in Melcon Transformers and Electricals.
April 24, 2026
The US DoC has issued preliminary affirmative determinations in antidumping duty investigations, setting preliminary dumping margins of 123.04% for India, 35.15% for Indonesia and 22.46% for Laos.
April 23, 2026
The Global Solar Council has announced a new management and strategy board drawn from across the solar and storage industries.
April 23, 2026
Evren has secured US$600 million in financing to develop a 1GW hybrid firm and dispatchable renewable energy (FDRE) portfolio across Andhra Pradesh and Rajasthan.
April 21, 2026
Sterling and Wilson Renewable Energy (SWREL) has secured a contract from Coal India (CIL) for an 875MW grid-connected solar project.
April 21, 2026
According to Ember's Global Electricity Review 2026, renewables accounted for 33.8% of global power generation in 2025.

Upcoming Events

Upcoming Webinars
May 27, 2026
9am BST / 10am CEST
Media Partners, Solar Media Events
June 3, 2026
National Exhibition and Convention Center (Shanghai)
Solar Media Events
June 16, 2026
Napa, USA
Solar Media Events
October 13, 2026
San Francisco Bay Area, USA
Solar Media Events
November 3, 2026
Málaga, Spain