Take up of Indian government rooftop solar allotment halves but could rise again

December 1, 2017
Facebook
Twitter
LinkedIn
Reddit
Email
Developers will be provided with an option to take more capacity by submitting another bank guarantee. Credit: IIT/Cleanmax

There were no takers for over half of the capacity up for grabs in India’s 500MW government buildings rooftop tender, however the final installed capacities could still rise again.

Solar Energy Corporation of India (SECI) today released the ‘final list of bidders/developers’ in the 500MW Phase-I of its grid-connected government rooftop solar scheme.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Allotments under the CAPEX model are now at just more than 20MW, down from the 50MW offered in this tender. Meanwhile allotments under the RESCO model are now at under 206MW, down from the 450MW available.

The RESCO model – where the developer leases the rooftop system to the rooftop owner – saw a lowest tariff of INR2.20/kWh for an 11MW project in the Andaman and Nicobar Islands, a special category state, when the L1 tariffs were first announced. But now only 7.8MW of this has been allotted.

Mudit Jain, senior manager of consulting at Bridge to India, told PV Tech that after the L1 tariffs for each individual state, other bidders had to match that cost in a particular state before being provided a respective government building. They also had to submit a performance bank guarantee, the deadline for which has already passed.

Jain said that work on the listed projects has likely started. While some bidders would have not accepted the final bids and then dropped out, others would have been put off by a change in the subsidy scheme.

Jain added: “The clause for subsidy calculation was changed and the amendment of tender didn't capture the change properly. While the RESCO projects were not impacted, there was a significant deviation in subsidy calculation for CAPEX projects. As a result, there were very few takers who were willing to match the L1 price.”

He also said that when the tender initially came out the subsidy was fixed at 16,250 rupees per watt (US$252) once 80% of the capacity is completed.

In the revised draft, SECI removed the fixed element of the subsidy, making it 25% of the quoted price, 25% of the benchmark capacity or 15,000 rupees per watt, whichever is lower. However, the Ministry of New and Renewable Energy's draft mentioned 25% of project cost. This created confusion and led to projects not being viable under the CAPEX model.

Jain added that on top of the L1 price matching and subsidy change issues, it is also possible that some developers were awarded buildings and found they could not build the required solar capacity on that building.

However, Jain also noted that these final allotments won’t necessarily correspond with final installations, because these developers will be provided with an option to take more capacity by submitting another bank guarantee.

The final list of Capex and Resco allotments can be found here.

Back in April, SECI reduced the solar capacity to be tendered on government buildings from 1GW to 500MW after a buildings survey came out with lower potential figures.

Read Next

October 16, 2025
Jakson Green and Blueleaf Energy have reached financial close for the 840MWp Bikaner solar projects in Rajasthan, western India. 
October 15, 2025
Wood Mackenzie has warned of a supply bottleneck as the renewable energy shift drives a spike in global copper demand over the next decade.
October 15, 2025
Ciel & Terre has launched a new floating PV structure designed to address the increasingly large scale of floating solar projects.
October 15, 2025
Indian module manufacturer Saatvik Green Energy, through its subsidiary Saatvik Solar Industries, has secured solar PV module orders worth INR6.89 billion (US$78 million).
October 14, 2025
India has installed 4.9GW of residential rooftop solar capacity in the first half of 2025, according to a report by IEEFA and JMK Research.
October 10, 2025
NTPC Renewable Energy Limited has signed an MoU with the Government of Gujarat to develop 15GW renewable energy projects in Gujarat.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
November 25, 2025
Warsaw, Poland
Solar Media Events
December 2, 2025
Málaga, Spain
Solar Media Events
February 3, 2026
London, UK
Solar Media Events
March 10, 2026
Frankfurt, Germany