EDF Renewables and Southern California Public Power Authority sign PPA for Bonanza solar-plus-storage plant

Facebook
Twitter
LinkedIn
Reddit
Email
Puerto Rico solar-plus-storage project.
EDF Renewables first applied for permission to build the project in late 2020, and plans to complete the permitting process by the end of 2025. Image: Lord Construction.

EDF Renewables North America has signed a power purchase agreement (PPA) with the Southern California Public Power Authority (SCPPA) to sell some of the power generated from its upcoming 300MWac Bonanza solar-plus-storage project in the state of Nevada, US.

The project will combine PV generation and a 195MW 4-hour battery energy storage system (BESS). Of this capacity, 125MWac of electricity generation capacity, and 65MW of the BESS capacity, will be sold to SCPPA by the end of 2028.

This article requires Premium SubscriptionBasic (FREE) Subscription

Unlock unlimited access for 12 whole months of distinctive global analysis

Photovoltaics International is now included.

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Unlimited digital access to the PV Tech Power journal catalogue
  • Unlimited digital access to the Photovoltaics International journal catalogue
  • Access to more than 1,000 technical papers
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

“Bonanza adds to SCPPA’s current portfolio of renewable energy projects, bringing the total to over 3,000MWs that will be supplied through SCPPA to Southern California Public Power Utilities to support their transition to a carbon-free energy future,” said Michael Webster, SCPPA executive director.

EDF Renewables first applied for permission to build the project in late 2020, and plans to complete the permitting process by the end of 2025. The developer is yet to complete three permitting processes, including producing an environmental impact statement and compliance with endangered species legislation, but the signing of a PPA suggests both EDF Renewables and SCPPA are optimistic that the project will receive a green light from the Department of the Interior and Bureau of Land Management.

The project is also being developed through title 41 of the Fixing America’s Surface Transportation Act (FAST). The FAST-41 process aims to accelerate the permitting of construction projects in a number of industries, including renewable energy production and electricity transmission, and a number of solar-plus-storage projects have received permits under this scheme, including the Desert Quartzite project in California and the Gemini project in Nevada.

Accelerating the permitting process

The acceleration of the permitting process has become a priority in recent years for the US renewable sector, with the White House’s Council on Environmental Quality proposing new rules to further streamline the process last July.

The quality of grid infrastructure is a key challenge for the global energy transition, with availability of grid connections, rather than political will or financial investment, often the limiting factor for the commissioning of new renewable power.

Alex Whitworth, head of Asia Pacific power research at Wood Mackenzie, told PV Tech Premium that China’s grid investments have increased by 60% in the last decade specifically to counter this problem, and the recent wave of new legislation in the US suggests the country is following suit.

PV Tech’s publisher Solar Media will host the 6th Energy Storage Summit USA, 19-20 March 2024 in Austin, Texas. Featuring a packed programme of panels, presentations and fireside chats from industry leaders focusing on accelerating the market for energy storage across the country. For more information, go to the website.

22 May 2024
London, UK
At the time of writing, Europe had had its most successful year in terms of Power Purchase Agreements (PPAs) with a record 7.8GW of renewable energy contracts signed. As we gather in May 2024 for the third edition of the Renewable Energy Revenues Summit, the energy landscape continues to evolve rapidly, influenced by the beating drum of climate change, volatility around power prices and the need to decarbonise power procurement as well as generation.
18 March 2025
Texas, USA
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2025!

Read Next

Subscribe to Newsletter

Upcoming Events

Solar Media Events
May 1, 2024
Dallas, Texas
Solar Media Events
May 21, 2024
Sydney, Australia
Solar Media Events
May 21, 2024
Napa, USA