Silevo technology ditched as Tesla’s Buffalo fab run by Panasonic

Facebook
Twitter
LinkedIn
Reddit
Email
Gigafactory 2 is to be ramped to its 1GW nameplate capacity exclusively by Panasonic in 2019. Image: Tesla

Panasonic’s solar manufacturing deal with Tesla at the former SolarCity 1GW solar cell and module assembly plant at RiverBend, Buffalo, New York State, which was recently renamed Gigafactory 2 by Tesla is to be ramped to its 1GW nameplate capacity exclusively by Panasonic in 2019. 

Initial production of solar cells at Gigafactory 2 for Tesla’s new roofing tiles product range is still expected to be operational in the summer of 2017, according to Tesla’s annual financial report for 2016. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The wording in the financial report regarding Panasonic’s role at Gigafactory 2 indicates that Panasonic’s high-efficiency HIT (Heterojunction with Intrinsic Thin layer) cells and modules would be ramped to its 1GW annual capacity, beginning in 2019.

‘This agreement provides that Panasonic will manufacture custom photovoltaic (PV) cells and modules for us, primarily at Gigafactory 2, and that we will purchase certain amounts of PV cells and modules form Panasonic during the 10-year term, with the intent to produce PV cells and modules totaling approximately 1 gigawatt annually beginning in 2019.’

PV Tech recently highlighted a number of known unknowns regarding the Tesla/SolarCity/Silveo/Panasonic solar manufacturing relationship and specifically the role (if any) of the Silevo cell technology that was initially planned to be produced at the facility and formed the key contractual obligations between SolarCity and with the Research Foundation for the State University of New York that would be responsible for the construction and equipment investment totalling US$750 million by New York State. 

Simply put, the Buffalo facility in its current footprint would not be able to produce both the Silevo and Panasonic cells and modules at 1GW capacity levels. 

However, the nail in the coffin for SolarCity’s Silevo technology adoption can also be found in Tesla’s annual report and does not leave much room for misinterpretation. 

‘As of December 31, 2016, the Company determined that the two remaining milestones will not be achieved by Silevo. As a result, the Company changed the estimated probabilities and adjusted the accrued contingent consideration balance to $0, for the two remaining milestones.'

Accordingly, the Company recognized a gain of $84.0 million, which is included as an offset to general and administrative expense.’

Silevo had three key milestones to meet for its investors to receive full remuneration of the US$200 million all stock transaction that stood at a further US$150 million in respect to milestones. SolarCity said at the time that the change would relate to Silevo investors that reside outside the US (China).

The revised acquisition terms between SolarCity and Silevo included the following:

1.    Silevo completes a new research and development production facility in the US that is capable of volume production with target efficiency requirements. 
2.    Silevo achieves both volume production with target efficiency requirements an at the R&D facility, while also completing and commissioning its first 1GW facility.
3.    Silevo achieves volume production with target cost and efficiency requirements from the 1GW facility, all before December 31, 2017.

Initially, payouts were planned in two 50MW ramp phases at US$50 million a phase, and a final US$50 million in earnings for a 100MW production ramp and production cost level (undisclosed) by 2016.

SolarCity noted that it had agreed to fund Silevo’s planned capacity expansions according to the revised plans, while all three phases of the earn-outs were now fixed. 

With the two remaining milestones cancelled as well as the payouts, speculation over the Silevo involvement in Gigafactory 2 can be put at and end. 

Separate SolarCity financial filings also reveal that its headcount declined by almost 20% by the end of 2016, which included manufacturing job losses. These would possibly relate to Silevo’s 100MW pilot line in Fremont, California, which is related to the first of three milestones related to the acquisition terms and conditions set by SolarCity.

With Panasonic investing its own money in Gigafactory 2 and responsible for supplying 1GW of solar cells and modules per annum in 2019, Tesla is potentially liable to pay financial penalties to the NY Research Foundation.

According to Tesla’s annual report: 

‘Although we continue to remain on track with our progress at Gigafactory 2, our expectations as to the cost of building the facility, acquiring manufacturing equipment and supporting our manufacturing operations may prove incorrect, which could subject us to significant expenses to achieve the desired benefits.’  

Tesla’s annual report highlighted that:

‘If we fail in any year over the course of the term of the agreement to meet these obligations, we would be obligated to pay a “program payment” of $41.2 million to the Foundation in such year.’

It remains unclear at this time if these clauses can be amended or whether Tesla would be obliged to pay $41.2 million every year of the 10 year agreement. 

16 June 2026
Napa, USA
PV Tech has been running PV ModuleTech Conferences since 2017. PV ModuleTech USA, on 16-17 June 2026, will be our fifth PV ModulelTech conference dedicated to the U.S. utility scale solar sector. The event will gather the key stakeholders from solar developers, solar asset owners and investors, PV manufacturing, policy-making and and all interested downstream channels and third-party entities. The goal is simple: to map out the PV module supply channels to the U.S. out to 2028 and beyond.
13 October 2026
San Francisco Bay Area, USA
PV Tech has been running an annual PV CellTech Conference since 2016. PV CellTech USA, on 13-14 October 2026 is our fourth PV CellTech conference dedicated to solar manufacturing in the USA. From polysilicon, wafers, ingots, cells and modules, to critical component suppliers including glass and frames, the event connects every stage of the value chain under one roof. PV CellTech USA also brings together investors, innovators, manufacturers and industry stakeholders to collaborate and strengthen domestic solar manufacturing across the United States.
20 April 2027
Istanbul, Türkiye
PV Tech has been running PV CellTech Conferences since 2016. PV CellTech Global, on 20-21 April 2027, is the meeting place for everyone invested in the growth of PV manufacturing and advancement in cell technologies, which will drive us towards the installed capacity required to power the planet by 2050. This is a gathering of key stakeholders driving capital expenditure and technologies for new PV manufacturing plants across the globe to harness the opportunities the growth of PV represents out to 2050 and beyond. The conference takes place in one conference room, where all senior peers have the same shared experience of learning and unique insight, unmatched anywhere else in the solar industry events calendar.

Read Next

Premium
May 22, 2026
As trade dynamics shift, could the EU become the next big market for Indian solar suppliers? PV Tech Premium explores the outlook with Wood Mackenzie’s Yana Hryshko and IEEFA’s Charith Konda.
May 21, 2026
US solar glass producer Stewart Glass is expanding its facility in Ohio with a new production line expected in 2027.
May 20, 2026
GameChange Solar has partnered with First Solar to support the deployment of domestically manufactured thin-film solar modules in India. 
May 19, 2026
JinkoSolar has partnered with PM Green to supply 200MW of modules, as part of a broader collaboration covering up to 1GW of capacity. 
May 19, 2026
Alex Barrows and Molly Morgan of CRU lay out their predictions for the biggest themes at this year's Intersolar Munich and SNEC conferences.
May 15, 2026
ISC Konstanz is upgrading its cleanroom facilities to operate a fully integrated solar cell and module pilot line by Q3 2026. 

Upcoming Events

Upcoming Webinars
May 27, 2026
9am BST / 10am CEST
Upcoming Webinars
May 27, 2026
9am BST / 10am CEST
Media Partners, Solar Media Events
June 2, 2026
Johannesburg, South Africa
Media Partners, Solar Media Events
June 3, 2026
National Exhibition and Convention Center (Shanghai)
Solar Media Events
June 16, 2026
Napa, USA