Nearly 1TW of solar PV in US interconnection queues in 2022

Facebook
Twitter
LinkedIn
Reddit
Email
Projects built between 2018-2022 can take up to four years to be completed in the US. Image: Unsplash

Nearly 1TW of solar PV capacity was in US interconnection queues at the end of 2022, according to a research from Lawrence Berkeley National Laboratory (LBNL).

With 947GW of generating capacity awaiting connectivity, solar had the largest share of generation capacity in the queue. Combined with wind, both technologies reached more than 1,250GW of capacity awaiting transmission access, nearly the same amount as the entire US power fleet currently installed.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

In total, renewables and storage totalled nearly 2TW of interconnection queues by the end of 2022, up 40% from last year when 930GW of zero-carbon capacity was awaiting transmission access.

The sum of solar, wind and storage capacity queuing for a connection would exceed the amount necessary for the US to reach 90% of electricity from zero-carbon resources by 2035.

Despite slow-downs from two of the largest grid operators – CAISO and PJM – the demand for grid access did not slow down in 2022. Due to the major influx of new interconnection requested in 2021, CAISO halted new requests in 2022, in order to process its backlog. Whereas PJM paused any new interconnection reviews until at least 2025, according to LBNL.

Moreover, hybrid projects account for a large and increasing share of proposed projects, most notably in California Independent System Operator (CAISO) and the non-ISO West markets. There were 457GW of solar hybrid projects – mainly solar and storage – in the queue, while more than half of the battery storage capacity waiting for transmission access was paired with some form of generation, primarily solar.

Interconnection queues indicate that commercial interest in hybrid projects has grown significantly. Source: LBNL.

“The interconnection queues illustrate both the opportunity and challenges of electric sector decarbonisation in the US,” said Joseph Rand, energy policy researcher at Berkeley Lab and lead author of the study.

“On the one hand, we see unprecedented interest and investment in clean energy development. On the other hand, the increasing delays and high withdrawal rates point to a major barrier for developers of these projects,” added Rand.

The ever growing backlog of renewable projects awaiting connection has become a major bottleneck for developing these projects as they take more time to complete the interconnection study process and come online, with most of the interconnection requests ending up cancelled or withdrawn.

Despite the more than 2TW of interconnection queues registered at the end of 2022, the major backlog for projects to get grid clearance showed that only 21% of the projects – and 14% of capacity – who sought capacity between 2000 and 2017 ended up reaching commercial operations.

More recent projects have been taking much more time and until later stages of the interconnection process to determine whether to cancel or withdraw the application.

“Later-stage withdrawals can be more costly for developers and can disrupt assumptions built into other projects’ interconnection studies, potentially delaying other projects”, said co-author Rose Strauss, of Berkeley Lab.

The timeline from grid request to commercial operation takes on average more than three years nowadays. At the beginning of the century, between 2000-2007, projects took more than two years, while those built in 2018-2022 can take more than four years.

Last year, the North American Electric Reliability Corporation (NERC) wrote for PV Tech Premium about the key considerations – and difficult balance – of managing grid connection from a transmission operator’s point of view.

Read Next

September 25, 2025
Developer ACE Power and Osaka Gas Energy Australia have submitted plans for a 100MW solar-plus-storage project to Australia’s EPBC Act.
September 24, 2025
The development of India’s power transmission network is lagging behind the country’s rapid growth in renewable energy, leading to project delays and cost increases
Premium
September 22, 2025
IREC’s Vaughan Woodruff considers the critical need for state-level reforms in readiness for the next shift in federal policy.
September 21, 2025
Lightsource bp has commenced work on a co-located battery energy storage system (BESS) at a 585MWdc solar PV plant in Australia.
September 17, 2025
For the third year in a row, self-consumption installs have fallen in Spain, with 611MW of new additions in the first half of 2025, according to a report from trade body APPA Renovables.
Premium
September 15, 2025
The UK government and solar industry have jointly published a long-anticipated roadmap detailing how to maximise the country’s solar potential. Chris Hewett, CEO of Solar Energy UK takes a closer look at the details.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
October 21, 2025
New York, USA
Solar Media Events
November 25, 2025
Warsaw, Poland
Solar Media Events
December 2, 2025
Málaga, Spain
Solar Media Events
February 3, 2026
London, UK